DOC - Permit Finaled | 5/20/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Andy J. Long
|
|
|
Completed home is now landscaped and stabilzed and listed for sale. ESC permit conditons stisfied. Two townhomes in progress adjacent to site by same contractor
|
Site Final | 3/23/2015 | 3/23/2015 | 3/23/2015 | A | PART |
Andy J. Long
|
|
|
Construction complete and sidewalk street have been swept.
1627 has been finaled. Need to clear materials (wattles, concrete chunks) from adjacent lot to close out permit.
No runoff or issues at site.
|
Aging Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 | | PASS |
Andy J. Long
|
|
|
Home construction is complete. Work ongoing on detached garage. BLD open. Yard is not yet finished but loose dirt is surround by perimeter wattle. Approved.
|
Aging Inspection | 12/10/2014 | 12/10/2014 | 12/10/2014 | | PASS |
Andy J. Long
|
|
|
Home is near completion. Landscaping and stabilization not yet acheived. No sediment or discharges leaving site. Perimeter wattle installed; permit posted.
|
Random Inspection | 10/9/2014 | 10/9/2014 | 10/9/2014 | P | PASS |
Andy J. Long
|
|
|
Permit posted. Perimeter wattles were initially installed, but have been removed at front for construction. No sediment leaving site and housekeeping is in compliance. Approved.
|
Site Preparation | 6/18/2014 | 6/19/2014 | 6/19/2014 | A | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|