Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberESC14-00200
StatusFinaled
Name BERNE HOTCHKISS
Site Address 2653 S VICTORY VIEW WAY
Project NameInvolta Data Center
Customer Number 
ePlanReviewNo
Description
Grading permit for new commercial building, parking lot and related landscaping.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled6/26/20156/26/20156/26/2015PPASS
DetailsAndy J. Long
General Inspection6/26/20156/26/20156/26/2015 PASS
DetailsAndy J. Long
Data center grounds are contained by vegetated berm and all stormwater is treated & retained on site. Area to the west of the building is over 50% vegetated with grasses and weeds. No fugitive dust issues or observable erosion so determined to be low risk and revegetated in fall after temperatures lower.

All temporary BMPs removed. Business is in operation.

No further ESC inspection necessary. Permit finaled.
General Inspection6/11/20156/11/20156/11/2015 PEND
DetailsEvan Jenkins
North and Eastsides of the building are still trying to establish vegetation
General Inspection5/27/20155/27/20155/27/2015 PASS
DetailsAndy J. Long
North side of site is still in process of revegetation
General Inspection5/12/20155/12/20155/12/2015 PEND
DetailsAndy J. Long
Grass is not establishing in many of the data center grounds that have been hydroseeded. Layer of tacifier still keeping soil stabilized. No fugitve dust issues observed or reported.

Talked to resident adacent to Idaho Power access road and Involta easement. Claims area where new fiber optic was installed causes lots of dust issues. Also Idaho Power needs to oil/stabilize the road. Will contact Idaho environmental compliance/maintenance division to see what schedule for road maintenance is. May need to have Involta hydroseed area.
General Inspection4/27/20154/27/20154/27/2015 PASS
DetailsAndy J. Long
Re-vegetation of data center grounds is still in progress. Grass is not growing on all locations, but the soil is secure with tacifier/hydroseed mix. No offisite discharges or issues. Will continue to monitor.
General Inspection4/10/20154/10/20154/10/2015 PASS
DetailsAndy J. Long
Hydroseeded areas north of data center are growing well. No trackout or issues, will continue to monitor to ensure grass is established. No corrections.
General Inspection3/26/20153/26/20153/26/2015 PASS
DetailsAndy J. Long
Hydroseeding is growing well. Stabilization near completion. No issues, Involta is open for business.
General Inspection3/11/20153/11/20153/11/2015 PASS
DetailsAndy J. Long
Involta Data Center is complete and operational. The site grounds and stormwater retention pond were hydroseeded this week. Coverage looks good.

Will keep permit open to check that grass will grow. No violations at site.

Note: Trench work along Victory View in ROW by seperate contractor was not cleaned up. Calling ACHD inspector to see if I can get a contact to clean it up.
General Inspection2/24/20152/24/20152/24/2015 PASS
DetailsEvan Jenkins
Waiting for seed to germinate. no esc issues
General Inspection2/9/20152/9/20152/9/2015 PASS
DetailsAndy J. Long
Construction on Involta Data Center is complete. All parking lots, drainage and other untilities have been installed and cleaned of loose sediment and construction materials.

Temp Occupancy issued for bond on the native grass seeding that will occur. ESC permit will stay open to monitor revegetation which will begin as conditions allow. No corrections needed.
General Inspection1/23/20151/23/20151/23/2015 PASS
DetailsEvan Jenkins
waiting for final stabilization to occur via landscaping/sod etc....
General Inspection1/8/20151/8/20151/8/2015 PASS
DetailsEvan Jenkins
Project near complete
No ESC issues at this time
General Inspection12/24/201412/24/201412/24/2014 PASS
DetailsEvan Jenkins
Tracking Control12/9/201412/9/201412/9/2014PPASS
DetailsAndy J. Long
Observed trackout out onto Maple Grove from the alternate access road to site. Checked on site and found that the tracks were actually not due to construction access and Involta traffic is using Victory View. Looks like trackout is either from someone playing in mud or Idaho Power operations adjacent to their facility.

Involta site is in progress and currently in compliance.
General Inspection12/5/201412/5/201412/5/2014 PASS
DetailsEvan Jenkins
Disturbed areas have been preped for landscaping/final stabilization. No esc issues observed at this time
General Inspection11/20/201411/20/201411/20/2014 PASS
DetailsAndy J. Long
Interior work ongoing. Parking lot and access road are paved so no trackout issues. No discharges or sediment runoff leaving site at time of inspection. Snow expected to melt over coming weekend so site will be re-inspected.
General Inspection11/4/201411/5/201411/5/2014PPASS
DetailsAndy J. Long
Involta data center parking lot and drive has been paved for some time. No trackout or areas where sediment is leaving site. A landscaped berm has been installed as well as some trees. Work on the data center is in progress, most interior. No ESC violations observed. Approved.
General Inspection11/4/201411/4/201411/4/2014 CANC
DetailsAndy J. Long
rescheduled for 11/5
General Inspection10/20/201410/20/201410/20/2014 PART
DetailsAndy J. Long
Entrance to Involta is now paved eliminating trackout issues. Crew onsite installing landscaping and irrigation lines. Exterior fram is built with work remaing on the interior. No dust or nonstormwater discharges observed.

Crew installing fence posts is not using a designated washout and has washed out in a few seperate places along fence line. Berm to the east of building is tracked vertically which could cause rill erosion is not regraded/stabilized.

Two verbal corrections to RP Bernie
1. Make fence crew use designated lined washout.
2. Retrack berm or provide schedule for stabilization.
Random Inspection10/2/201410/2/201410/2/2014APASS
DetailsAndy J. Long
No trackout or dust issues observed at Involta Data Center site. Permits are posted, utility trench is in progress along the future entrance/construction access. Soon it will be paved, if not new rock will be required.

No corrections at this time.
General Inspection9/19/20149/19/20149/19/2014 PASS
DetailsAndy J. Long
Involta Data Center is in progress. Permit and SWPPP are posted at entrance to site.

There is a silt fence surrounding the site, some areas have come loose but the sediment containment berm has been created around site, so no sediment leaving area of disturbance. No trackout to Victory View - looks like access road will be installed soon. Entrance off Maple Grove has been blocked to prevent dust from construction vehicle traffic.

No corrections at this time.
General Inspection9/4/20149/4/20149/4/2014 PASS
DetailsEvan Jenkins
Silt Fence still in pretty good shape
majority of the curbs have been poured
no esc issues at time of inspection
General Inspection8/20/20148/20/20148/20/2014 PASS
DetailsAndy J. Long
Frame for Involta data center is being built. Site utilities and permanent stormwater controls have been installed.

Construction entrance on Victory View has been removed and graded to prep for paving of parking lots and access drive. Minimal trackout to street, stormdrains have inlet protection.

No dust issues at time of inspection, perimeter silt fence is in good condition, and signage was posted on entrance off Maple Grove to keep dust from traffic down.

Site is currently in compliance.
General Inspection8/5/20148/5/20148/5/2014 PASS
DetailsEvan Jenkins
General Inspection7/18/20147/18/20147/18/2014 PART
DetailsEvan Jenkins
a bit dusty, but nothing too major. Contacted Bernie and left a VM disclosing issue
Complaint Inspection7/3/20147/3/20147/3/2014APART
DetailsEvan Jenkins
Call came in for no dust suppression
Talked with Bernie: he explained there was 1 semi that drove too fast down north access road causing dust. He stated he will keep a water truck running the road to keep the dust down
Random Inspection6/23/20146/23/20146/23/2014PPASS
DetailsAndy J. Long
Victory View had some trench work by the construction access that has not been patched over yet, some minor trackout. DI's have protection though. Some dust seen in air around site, but not excessive and there is a water truck on site. No corrections at this time. BMPs in good condition.
General Inspection6/10/20146/10/20146/10/2014 PASS
DetailsAndy J. Long
Permit posted and SWPPP binder at entrance. Completed inspection reports are kept inside the job trailer. No significant track out or dust. No corrections at this time. Discussed project with RP Berne who was onsite.
General Inspection5/22/20145/23/20145/23/2014APASS
DetailsAndy J. Long
Involta Data Center site has been graded and compacted. Crews onsite installing underground utilities.

Perimeter silt fence is good condition and wide buffer seperates the creek to the north. Construction entrance is large grade rock and effective, some minor trackout to street can be swept at end of day. Permit posted, SWPPP on site.

No corrections at this time.
General Inspection5/22/20145/22/20145/22/2014 CANC
DetailsAndy J. Long
Rescheduled for 5/23
Random Inspection5/7/20145/7/20145/7/2014PPASS
DetailsAndy J. Long
Went to check on conditions at site when in the area. Silt fence perimeter is in good conditions vegetated buffer between 10 mile creek. Construction entrance is to be removed and paved once utilities are installed (next week per site superintendant/RP. No corrections at this time.
Complaint Inspection4/24/20144/24/20144/24/2014PPASS
DetailsEvan Jenkins
no isses with ESC
Random Inspection4/22/20144/22/20144/22/2014PPASS
DetailsAndy J. Long
Construction entrance has heavy duty rock. Minimal trackout through muddy day. Permit posted at entrance, DI's on Elisa and Victory View protected. Approved.
Site Preparation4/8/20144/11/20144/11/2014APASS
DetailsAndy J. Long
Berne Phone #: ###-####

Perimter BMPs installed properly. Discussed SWPPP and ESC plan with Project Manager and RP Berne and Dave E. from Syman. Grubbing is to start early next week. Current access is off Maple Grove, but the official entrance and permit is at Victory View. Access will be installed Monday or Tuesday. Official groundbreaking is next Wednesday. No dewatering anticipated, actually hauling in dirt from offsite. Washout to be placed in SE corner near job trailor, going to used bermed pit lined with visquine.

eNOIs filed by contractor (Rinderknecht) and owner (Involta), IDR12E477 and IDR12E704 respectively.

Approved for excavation.