Permit Information
Permit NumberESC14-00238
StatusFinaled
Name JIM CONGER
Site Address 6800 E WARM SPRINGS AVE
Project NameEAST VALLEY SUBDIVISION
Customer Number 
ePlanReviewNo
Description
Offsite utilitiy installation for the new subdivision. Installation of new sewer trunk line and water line to the East Valley Subdivision. Most work will be conducted in ACHD R.O.W., seperate permits may apply. Related to ESC14-00022, ESC14-00144. No dewatering is anticipated at time of review. Site Prep inspection required. Permit covers staging area for utility project as well.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/17/20146/17/20146/17/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled6/17/20146/17/20146/17/2014PPASS
DetailsAndy J. Long
Utilities (sewer/water) have been extended out to East Valley Sub. Warm Springs has been repatched and shoulders restored. Constrution materials and BMPs have been removed. No further construction for this permit. See ESC14-00144 for East Valley Sub main site ESC permit.
Random Inspection6/2/20146/2/20146/2/2014PPASS
DetailsAndy J. Long
WIP. Crew continuing work on repaving east bound land of Warm Springs. Trench is installed. Brooms onsite, no stormwater structures or surface water adjacent to construction area.

No corrections.
Random Inspection5/16/20145/16/20145/16/2014PPART
DetailsAndy J. Long
Installation of offsite utilities is currently inactive. First phase is complete and roads were swept. One portion of road has not been paved and dust is being kicked.

Advised to post traffic control sign to slow vehicle down, creating less dust. Left VM to Jim Conger.
General Inspection5/2/20145/2/20145/2/2014 FAIL
DetailsEvan Jenkins
Verbal warning to Mr. Conger about fugitive dust. Drove by for my inspection, watched to side dump trucks exit and dust was boiling out all over. There's 3-4 inches of pounder dust throughout all access roads. Mr. Conger stated he is on it right now, and will install a construction entrance that's currently being used onto Warm Springs Road. Currently no construction entrance. Entire site needs to be watered down and entrance installed. Will follow up Monday
Complaint Inspection4/16/20144/16/20144/16/2014APART
DetailsAndy J. Long
Fugitive dust complaint(s) called into Code Enforcement yesterday afternoon.

Called RP Jim Conger to discuss issue and he stated he increase the number of water trucks out there and focus on the areas of truck traffic and grading. IT should be noted it is also very windy this week.

Stockpiles in the middle of development have been inactive more than 2 weeks and should be stabilized with hydroseed or mulch if no plans to remove. Will make request to Conger and follow up.