Site Final | 3/13/2015 | 3/13/2015 | 3/13/2015 | A | PASS |
Andy J. Long
|
|
|
Dykman warehouse building is complete and no loose sediment or materials remain on site.
Landscaping and installation of irrigation lines is finished and sidewalks and gutters have been swept.
Temp BMPs including MS4 drop inlet sediment bags have been removed.
ESC permit finaled.
|
DOC - Permit Finaled | 3/13/2015 | 3/13/2015 | 3/13/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 | | PASS |
Andy J. Long
|
|
|
Warehouse construction is complete. No activity at site. Still need to complete landscaping, stabilization and remove the temporary BMPs (DI filter bags).
No sediment runoff or trackout at site. No corrections needed at this time. Will check back for landscaping etc.
|
General Inspection | 12/23/2014 | 12/23/2014 | 12/23/2014 | | PASS |
Andy J. Long
|
|
|
Warehouse near completion. No trackout. BMPs installed.
|
General Inspection | 11/7/2014 | 11/7/2014 | 11/7/2014 | | PASS |
Andy J. Long
|
|
|
Permit posted, lined concrete washout pit being utilized. No significant trackout or sediment runoff, streets and gutters are clean and all receiving drop inlets have filter bag protection. WIP, no corrections required.
|
General Inspection | 9/22/2014 | 9/22/2014 | 9/22/2014 | | PASS |
Andy J. Long
|
|
|
Permit posted. Vertical construction in progress. BMPs installed are vehicle tracking pad and DI protection for MS4. No discharges or other violations observed.
|
General Inspection | 8/5/2014 | 8/5/2014 | 8/5/2014 | | PASS |
Evan Jenkins
|
|
|
work in progress 2 walls have been erected, and foundation poured. no esc issues at time of inspection
|
General Inspection | 6/18/2014 | 6/18/2014 | 6/18/2014 | | PASS |
Evan Jenkins
|
|
|
Construction signage posted next to construction entrance off latimer. Contractor currently sweeping curbs and sidewalks from subcontractors making small messes. No ESC issues at time of inspection
|