General Inspection | 5/15/2015 | 5/15/2015 | 5/15/2015 | | PASS |
Andy J. Long
|
|
|
Collission Center building is complete as well are the associated site improvements. No loose sediment or disturbed area at site. All construction materials have been removed. The LH Miller Honda is in progress across the street. DI bag can stay in on Auto Dr.
|
DOC - Permit Finaled | 5/15/2015 | 5/15/2015 | 5/15/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/30/2015 | 3/30/2015 | 3/30/2015 | | PASS |
Andy J. Long
|
|
|
Some work is still in progress, streets and gutters in auto mall are free of trackout & sediment. The drop inlets on Auto drive have sediment protection. No discharges, dust or other issues observed.
|
General Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 | P | PASS |
Andy J. Long
|
|
|
Larry H. Miller collision center expansion project is now in operation under temp. occupancy. Parking lot still has some areas needing paving as well as landscaping. No trackout to Auto Drive, streets and gutters have been recently swept.
No corrections needed. Will continue to monitor stabilization of loose dirt. See also ESC14-00486 (carwash and south parking lot)
|
General Inspection | 2/10/2015 | 2/10/2015 | 2/10/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/26/2014 | 12/26/2014 | 12/29/2014 | | PASS |
Andy J. Long
|
|
|
Building frame and footprint is up and interior work is ongoing. Area of disturbance is surrounded by construction fencing, permit posted on fence. Some areas of parking lot/access drive pavement have not yet been paved, but no trackout or discharges to Cole or Auto Drive. No violations cited at site.
|
General Inspection | 11/10/2014 | 11/10/2014 | 11/10/2014 | | PASS |
Andy J. Long
|
|
|
WIP on LHM Collision Center. No sediment or discharges leaving site. Vertical construction in progress. Drop inlets have filter bag containment protection and ESC permit posted visibly on security fencing. No corrections at this time.
|
Random Inspection | 9/24/2014 | 9/24/2014 | 9/24/2014 | A | PEND |
Andy J. Long
|
|
|
Vertical construction is in progress at LHM Auto Center for the collision repair center. No dust or trackout issues and BMPs are installed.
Did not see permit sign or SWPPP signage and site has a CGP. Also work for BLD14-01545 appears to be occuring without having picked up the permit.
|
General Inspection | 8/20/2014 | 8/20/2014 | 8/20/2014 | | PASS |
Andy J. Long
|
|
|
WIP on collision center addition. Drainage features have filter protection and existing hard surfaces have been preserved. Concrete washout facility located at south end of Auto Drive. No trackout, dust, or other issues. Approved.
|