General Inspection | 3/15/2016 | 3/15/2016 | 3/17/2016 | | PASS |
Andy J. Long
|
|
|
Yard landscaped, building materials removed as requested and DI bag on Ashtree was taken out. ESC permit conditions satisfied.
Approved.
|
DOC - Permit Finaled | 3/17/2016 | 3/17/2016 | 3/17/2016 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 2/29/2016 | 2/29/2016 | 3/1/2016 | P | NR |
Andy J. Long
|
|
|
Scott ###-####
Need to remove trash and building materials from adjacent lot. Stabilize disturbed area and remove DI bag
|
General Inspection | 2/25/2016 | 2/25/2016 | 2/25/2016 | | PEND |
Evan Jenkins
|
|
|
establishment of perm vegetation
|
General Inspection | 2/10/2016 | 2/10/2016 | 2/10/2016 | | PASS |
Andy J. Long
|
|
|
Home complete. Site revegetation in progress. No corrections needed.
|
General Inspection | 1/26/2016 | 1/26/2016 | 1/26/2016 | | PASS |
Andy J. Long
|
|
|
Near completion. WIP on interior and not yet landscaped. No sediment or other construction materials leavings site.
|
General Inspection | 1/11/2016 | 1/11/2016 | 1/11/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/25/2015 | 12/25/2015 | 12/28/2015 | | CANC |
Andy J. Long
|
|
|
Christmas holiday
|
General Inspection | 12/10/2015 | 12/10/2015 | 12/11/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 | | PASS |
Andy J. Long
|
|
|
WIP on interior. No trackout, no sediment leaving site.
|
General Inspection | 11/10/2015 | 11/10/2015 | 11/10/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/26/2015 | 10/26/2015 | 10/26/2015 | | PASS |
Andy J. Long
|
|
|
WIP on interior. Trash and materials are contained, perimeter vegetation has been preserved. No trackout or discharges. Approved.
|
General Inspection | 10/9/2015 | 10/9/2015 | 10/12/2015 | | PASS |
Andy J. Long
|
|
|
WIP on interior. No active earth work. No sediment runoff or significant trackout observed.
Trash and materials contained on site. Surround native vegetation has been preserved where possible. No corrections at this time, but will want to empty out the sediment bag at bottom of Ashtree soon, over 50% capacity.
|
General Inspection | 9/24/2015 | 9/24/2015 | 9/24/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/9/2015 | 9/9/2015 | 9/10/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/25/2015 | 8/25/2015 | 8/25/2015 | | PASS |
Andy J. Long
|
|
|
WIP on SFH. No trackout or loose dirt leaving site. Staying within clearing limits. Trash and materials are contained. No corrections.
|
General Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 | | PASS |
Andy J. Long
|
|
|
WIP. Frame is up. No trackout or discharges observed. Permit sign posted. Staying well within clearing limits to preserve existing vegetation.
|
General Inspection | 7/24/2015 | 7/24/2015 | 7/24/2015 | | PASS |
Andy J. Long
|
|
|
WIP on frame. No earth moving activity, site is mostly stabilized around perimeter with BMPs installed.
No trackout or discharges, no windblown litter. Clean site.
|
General Inspection | 7/9/2015 | 7/9/2015 | 7/9/2015 | | PASS |
Andy J. Long
|
|
|
Permit posted, activity remaining within limits of disturbance and preserving existing vegetation and rock features. No trackout or discharges. No activity at time of inspection.
|
General Inspection | 6/24/2015 | 6/24/2015 | 6/24/2015 | P | PASS |
Andy J. Long
|
|
|
No trackout or sediment leaving site. Limits of disturbance have not expanded to surrounding vegetation. Approved.
|
General Inspection | 6/12/2015 | 6/12/2015 | 6/12/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 5/28/2015 | 5/28/2015 | 5/28/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: Framing is currently taking place. No ESC issues at this time
|
General Inspection | 5/13/2015 | 5/13/2015 | 5/13/2015 | | PASS |
Andy J. Long
|
|
|
Foundation slab and driveway are now complete. Wattle protecting onsite swale from sediment is in good condition. Very clean site, keeping well with limits of disturbance. Permit sign is posted. No corrections required.
|
General Inspection | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Andy J. Long
|
|
|
Permit posted. Swale still has perimeter sediment protection. Site has been kept clean throughout project. Approved.
|
General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Andy J. Long
|
|
|
Dirt offhauling is finished for time being. Work is occuring to prep for foundation. No trackout, permit posted, construction entrance and sediment control BMPs are installed on stormwater infrastructurs (swale onsite, inlet on street)
Approved, no corrections necessary at this time.
|
General Inspection | 3/31/2015 | 3/31/2015 | 3/31/2015 | | PASS |
Andy J. Long
|
|
|
WIP. Permit posted, construction entrance and wattles installed per ESC plan.
Still offhauling dirt and rock offsite. No significant trackout or other violations.
|
Site Preparation | 3/13/2015 | 3/16/2015 | 3/16/2015 | A | PASS |
Andy J. Long
|
|
|
Please call ahead to meet onsite - Scott Phone #: ###-####
Pre-excavation meeting prior to earth disturbance. BMPs installed per ESC site map and include silt fence boundary and straw wattle protecting the drainage swale/french drain. Will protect existing vegetation on back slope.
Construction entrance will be installed after removal of approximately 800 yards of dirt stockpiled over time.
Permit posted. Approved to begin construction activity.
|