General Inspection | 1/30/2015 | 1/30/2015 | 1/30/2015 | | PASS |
Andy J. Long
|
|
|
Construction complete on all 4 Landmark Apartment buildings. Building materials and hard surfaces have been swept. All permits finaled and some apartments already occupied. DI bag will be removed by property management company when the dirty snow pile is finished melting. No further ESC inspections needed.
|
DOC - Permit Finaled | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Andy J. Long
|
|
|
Interior work on Landmark Apartments is being complete. 60% of site is landscaped; crew is onsite planting trees, installing irrigation system, and sod. Parking lot and entrance will need to be swept once landscaping is complte. BMPs installed, no trackout to Hackamore or stormwater pollution sources observed.
|
General Inspection | 11/26/2014 | 11/26/2014 | 12/1/2014 | | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 10/7/2014 | 10/7/2014 | 10/7/2014 | P | PASS |
Andy J. Long
|
|
|
Landmark Apartments in progress. No trackout or erosion issues at site. Perimeter wattles installed; trash and materials are being contained within staging area. Approved.
|
General Inspection | 9/24/2014 | 9/24/2014 | 9/24/2014 | | PASS |
Andy J. Long
|
|
|
All 4 Landmark apartment units are in progress. No trackout from site, no dust plumes observed. Stormwater infrastructure and paving are not yet installed and site's sheet flow is directed inward instead of offisite. Permit posted. Approved.
|
Site Preparation | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | CANC |
Mike Jordan
|
|
|
|
Random Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PART |
Mike Jordan
|
|
|
Needs to sweep silts from strret, empty concrete washout. Correction notice to RP.
|
Site Preparation | 7/21/2014 | 7/22/2014 | 7/22/2014 | P | PASS |
Andy J. Long
|
|
|
ESC inspection requested by Andersen Construction and Greg from Ground FX. Early afternoon.
Perimeter fiber wattles have been installed. Other BMPs include a construction entrance and DI protection on private drain across access road.
Water truck is onsite, and end of day sweeping and cleaning of dirt clods will be conducted per on site project manager Matt McCain of Lurre Construction.
Approved.
|