DOC - Permit Finaled | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 | | PASS |
Andy J. Long
|
|
|
Project complete and landscaped. Backyard parking area stabilized. ESC permit conditions met.
|
Site Final | 2/27/2015 | 2/27/2015 | 2/27/2015 | P | NR |
Andy J. Long
|
|
|
site final requested by Rocky ###-####
Need to clean up construction materials waste at site and stabilize alley driveway apron.
No violations, but work is still in progress. Notified Rocky to call when project is complete.
|
Aging Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 | | PASS |
Evan Jenkins
|
|
|
|
Aging Inspection | 12/4/2014 | 12/4/2014 | 12/4/2014 | | PASS |
Evan Jenkins
|
|
|
WIP
|
Site Preparation | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PASS |
Andy J. Long
|
|
|
1 PM Rocky ###-####
Met RP/GC Rocky Carpenter at site. Will be an addition/remodel to an exisitng home in north end. Project area is in backyard with access to alley.
Permit will be posted in front window and project to start the 2nd or 3rd week of July. Low risk site, no off site discharges anticipated.
|