Permit Information
Permit NumberESC14-00514
StatusFinaled
Name BRIAN ELLSWORTH
Site Address 450 W McGREGOR DR
Project NameCampbell Company
Customer Number 
ePlanReviewNo
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection5/5/20155/5/20155/5/2015 PASS
DetailsAndy J. Long
Drop inlet bag on MS4 on McGregor to the east of Campbell Co. has been removed as requested.

Bag to the west on McGregor will be removed when the adjacent project (ESC14-01030) is complete.

ESC permit conditions satisfied; permit finaled.
DOC - Permit Finaled5/5/20155/5/20155/5/2015PPASS
DetailsAndy J. Long
General Inspection3/20/20153/20/20153/20/2015 PART
DetailsAndy J. Long
Construction complete and site has been landscaped and hard surfaces swept. Silt fence BMP has been removed and vegetation/sage brush was preserved on the hillside.

1 correction:
Remove DI filter bags (2) on McGregor when removing EKC sign. Both bags are still in good condition.
General Inspection2/2/20152/2/20152/2/2015 PASS
DetailsAndy J. Long
WIP on new building for Campell Co. No trackout offsite to McGregor. MS4 DIs have protection, silt fence perimeter is still install along back of building. No violations observations.
Complaint Inspection12/16/201412/16/201412/16/2014PPART
DetailsAndy J. Long
excecessive trackout reported by Public Works environmental technician

Inspection found that trackout is located within interior parking access drive (private). No trackout to McGregor or accumulations in MS4 gutters.

Parking lot still should be swept this week to prevent further trackout offsite. Project manager Josh stated that curbing crews would sweep this week after finishing work. Onsite storm drain has sediment bag installed.

No other violations observed.
General Inspection12/4/201412/4/201412/4/2014 PASS
DetailsAndy J. Long
WIP at Campbell Co. See also ESC14-00499 for associated project. No trackout. DIs have filter protection. Permits post. Silt fence along hilltop is installed. No corrections.
General Inspection10/16/201410/16/201410/16/2014 PASS
DetailsAndy J. Long
WIP at Campbell Company. Silt fence at edge of hill/project boudary is staked and vegetation downslope is undisturbed. Permit posted. No trackout to Mcgregor and MS4 stormdrains have sediment protection.

Some trackout within the parking lot due to trenching. Currently not leaving site or affecting drainage facilities.
Site Preparation8/27/20148/28/20148/28/2014APASS
DetailsAndy J. Long
Josh Phone #: ###-####

Site walk through with project supervisor from EKC construction. All BMPs set up per ESC site plan, with one change to additional silt fence with wattle to the south of site. Permit posted and SWPPP is onsite. Approved.