Permit Information
Permit NumberESC14-00530
StatusFinaled
Name KEVIN HONEYCUTT
Site Address 2755 S BEVERLY ST
Project NameProject Beverly - N&T Holdings
Customer Number 
ePlanReviewNo
Description
Open Storage Shed
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled1/20/20151/20/20151/20/2015PPASS
DetailsAndy J. Long
ESC inspections for project Beverly by ESC to be covered at ESC14-00528 & 529. Multiple permits at same site with multiple buildings that will be on seperate parcels upon being developed. No issues at site.
General Inspection1/9/20151/9/20151/9/2015 PASS
DetailsAndy J. Long
WIP. Contractors staying off unfinished/dirt area and parking in completed parking lot as well as material staging. No dischages. No trackout. Approved.
General Inspection12/19/201412/19/201412/19/2014 PART
DetailsAndy J. Long
Beverly warehouse project is in progress. The first two warehouse frames have been erected and the parking lots and stormwater drainage have been constructed as well as the new channel/diversion for the irrigation drain that runs through site.

No trackout or erosion, onsite storm drains need inlet protection to protect underground seepage bed.

RP Kevin is now on new project, gave verbal correction to new site supervisor Phil who was onsite to install filter bags or mats. He said it will be done today.
General Inspection12/4/201412/4/201412/4/2014 PART
DetailsAndy J. Long
WIP at Beverly project. Trackout to Beverly is significant and is quite muddy. It is not extending to Victory and no stormwater infrastructure in area. Site is still quite and is also being paved, so sweeping will occur once it dries up (unless trackout worsens to Victory). No offsite discharges occuring. Just need to clean up trackout when conditions allow.
General Inspection11/5/201411/5/201411/5/2014 PART
DetailsAndy J. Long
Site perimeter BMPs and construction entrance are installed and permits are onsite in the office trailer. There is no water in the drainage/irrigation ditch that is adjacent to site.

Recent utility work on the shoulder and the road have left a significant amount of loose dirt. No MS4 structures and it is not tracking out to Victory.

Correction notice issued to Kevin to sweep Beverly once utility is fully complete and road is patched.
General Inspection10/2/201410/2/201410/2/2014 PASS
DetailsAndy J. Long
ESI project with 3 buildings on one large parcel off Victory is in progress with foundations just starting to be poured.

RP/Project Super Kevin is onsite with SWPPP. SWPPP site map has been updated with new inlet protection on Victory for offsite utility/water work to connect the site.

New heavy grade rock provided for entrance is keeping trackout in control. Irrigation drain work is complete and culverts installed. No flow at time of inspection.

Permit posted. Approved.