Permit Information
Permit NumberESC14-00531
StatusFinaled
Name CHRIS CONNER
Site Address 1020 E OPUS ST
Project NameYanke/Buker Residence
Customer Number 
ePlanReviewNo
Description
As per ESC conditions, New residential house
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection8/24/20158/24/20158/24/2015 PASS
DetailsAndy J. Long
Home complete, landscaped, and stabilized. ESC permit conditions satisfied.
DOC - Permit Finaled8/24/20158/24/20158/24/2015PPASS
DetailsAndy J. Long
Aging Inspection6/22/20156/22/20156/22/2015 PEND
DetailsAndy J. Long
Home is complete. No trackout or sediment leaving site, but need to remove remaining equipment and materials from adajacent lot, clean up any remaining trash and have temp dumpster pick up.
Aging Inspection4/22/20154/22/20154/22/2015 PASS
DetailsAndy J. Long
WIP. Home is being painted on exterior. Yard is not yet landscaped. No trackout or discharges. No illicit washout activity observed. Trash contained. No corrections.
Aging Inspection2/18/20152/18/20152/20/2015 CANC
DetailsAndy J. Long
Random Inspection12/19/201412/19/201412/19/2014PPASS
DetailsAndy J. Long
WIP. Exterior frame is up, interior work ongoing. No trackout, permit posted, site is very clean with no trash or uncontained litter. No corrections required.
Random Inspection9/22/20149/22/20149/22/2014APASS
DetailsAndy J. Long
SFH in progress. Workers staying off adjacent lot and preventing trackout . Permit is posted with contact info, no sediment accumulations in gutter. Site is looking good.
Random Inspection8/21/20148/21/20148/21/2014APASS
DetailsAndy J. Long
Permit posted. No trackout to street and minimal sediment in gutter in front of home. Foundation has been poured. Workers damaged fiber wattle by driving over it but no violations so okay.
Site Preparation7/31/20148/1/20148/1/2014APASS
DetailsAndy J. Long
Chris ###-####

Permit posted. Fiber wattle staked down along curb (will need to be removed during loading).

Approved for excavation, will start next week.