Site Final | 2/11/2015 | 2/12/2015 | 2/12/2015 | A | PASS |
Andy J. Long
|
|
|
Dan Appel Phone #: ###-#### Inspection requested via web by Daniel Appel
Construction complete, site mostly stabilized with some final landscaping in progress. Any loose sediment will be swept at end of day.
Permit conditions satisfied. Site final approved.
|
DOC - Permit Finaled | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 10/17/2014 | 10/17/2014 | 10/17/2014 | P | PASS |
Andy J. Long
|
|
|
Dan Appel Phone #: ###-#### >> Inspection requested via web by Daniel Appel
Permit posted. Flat site, no MS4 infrastructure on Warren. Approved for excavation.
|