General Inspection | 4/16/2015 | 4/16/2015 | 4/16/2015 | | PASS |
Andy J. Long
|
|
|
Grading & utility permit/phase is complete. Vertical constructionerosion sediment control covered under ESC14-00989. No outstanding ESC issues at site.
|
DOC - Permit Finaled | 4/16/2015 | 4/16/2015 | 4/16/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 | | PASS |
Andy J. Long
|
|
|
No activity or violations at site. Currently project on hold and is graded with utilities installed for further vertical construction.
|
General Inspection | 3/13/2015 | 3/13/2015 | 3/13/2015 | | PASS |
Andy J. Long
|
|
|
No construction activity occuring at this time. Perimeter wattles and DI protection installed to control sediment. No runoff or trackout from site.
|
General Inspection | 2/25/2015 | 2/25/2015 | 2/25/2015 | | PASS |
Andy J. Long
|
|
|
Site pad is prepped for further construction, but no currently activity/vertical construction. Utilities have been installed and lot graded flat. Perimeter wattles are treanched in and MS4 inlets are protected.
No corrections.
|
Random Inspection | 2/4/2015 | 2/4/2015 | 2/4/2015 | P | PASS |
Andy J. Long
|
|
|
Site is currently shut down but has good perimeter controls and was cleaned up before crews left. Need to repost permit sign that has been damaged by weather.
|
Site Preparation | 10/30/2014 | 10/30/2014 | 10/30/2014 | P | PEND |
Andy J. Long
|
|
|
Byion Phone #: ###-####
Construction to start next week. Need to post permit. Perimeter wattle is installed and construction entrance will be placed after initial site grubbing.
|
Site Preparation | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | NR |
Andy J. Long
|
|
|
Kevin Phone #: ###-####
Crew has not yet installed ESC controls; contractor Kevin will re-schedule site prep inspection when ready. No excavation yet.
|