General Inspection | 8/20/2015 | 8/20/2015 | 8/20/2015 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Evan Jenkins
|
|
|
ESC Conditions Satisfied
|
General Inspection | 8/5/2015 | 8/5/2015 | 8/5/2015 | | PEND |
Evan Jenkins
|
|
|
Carports Complete Interior Roads need final Sweeping from Carport work prior to permit being closed. Temp BMP's have been Removed
|
General Inspection | 7/21/2015 | 7/21/2015 | 7/21/2015 | | CANC |
Andy J. Long
|
|
|
no inspection, wip on carports. Next general inspection will check for temp BMP removal and final cleanup. Site already stabilized.
|
Site Final | 7/2/2015 | 7/6/2015 | 7/7/2015 | A | NR |
Andy J. Long
|
|
|
WIP on carports. Some loose dirt in unfinished section will be swept up before paint striping. No discharges, spills, or trackout. DI bags were removed previously but will wait till all work, equipment, and loose dirt is swept.
|
General Inspection | 7/2/2015 | 7/2/2015 | 7/2/2015 | | CANC |
Andy J. Long
|
|
|
Site final rescheduled for Monday July 6
|
General Inspection | 6/17/2015 | 6/17/2015 | 6/17/2015 | | PEND |
Evan Jenkins
|
|
|
Project has been completed, but Temporary BMP's still in Place (Drop Inlet Protection). Called Ken and disclosed if he gets the temp BMP's removed, I'll close the permit. Ken stated he will get somebody out here today to get them removed.
|
General Inspection | 6/2/2015 | 6/2/2015 | 6/2/2015 | | PEND |
Evan Jenkins
|
|
|
4-Plexes are complete, perm vegetation has been re-established. Remove Temp BMP's (Drop Inlet Protection) and large Blue PVC Pipe from sidewalk (Water Main Pipe) prior to this permit being closed
|
General Inspection | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | PASS |
Andy J. Long
|
|
|
Bristlegrove subdivision has been landscaped and all 7 units are near completion.
No discharges, trackout, or uncontained trash/materials. To final permit need to sweep parking lot and remove any remaining contruction equipment or materials. All 7 ESC permits for the individual units ESC14-00443 to -00449 were finaled 5/18
|
General Inspection | 5/4/2015 | 5/4/2015 | 5/4/2015 | | PASS |
Evan Jenkins
|
|
|
Area has been completely re-vegetated. Still some interior construction occuring. Permit shall be Finaled once area has been swept, and Temp BMP's have been Removed. No ESC issues at this time
|
General Inspection | 4/17/2015 | 4/17/2015 | 4/17/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: near completion. Landscaping in full action to establish vegetation. No ESC issues at this time
|
General Inspection | 4/2/2015 | 4/2/2015 | 4/2/2015 | | PART |
Evan Jenkins
|
|
|
Contacted Ken Skaggs via cell to disclose the internal streets and sidewalks need a good sweeping. He stated they will do so. All drainage stays on site via seepage beds. Will follow up at next inspection
|
General Inspection | 3/18/2015 | 3/18/2015 | 3/18/2015 | | PART |
Evan Jenkins
|
|
|
Streets need to be swept as well as sidewalks. Concrete washout needs to be replaced as well. Talked with Justin onsite. He stated they will sweep and address the concrete washout today
|
Aging Inspection | 2/6/2015 | 2/6/2015 | 2/6/2015 | | PASS |
Evan Jenkins
|
|
|
|
Random Inspection | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Andy J. Long
|
|
|
No activity at Bristlegrove Sub at time of inspection. Perimeter wattles are in place. Permit posted, no trackout, dust, or non-stormwater discharges observed. No corrections at this time.
|
Site Preparation | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PEND |
Andy J. Long
|
|
|
Bristle Grove sub inspection:
Utility work and rough grading at site appears to have commenced with out ESC or other permits. Checking with planning division to figure out if this was approved.
ESC BMPs are installed; no significant trackout and irrigation canal is protected with wattle and vegetated buffer.
Will check to see if correct process has been followed.
|
Site Preparation | 9/9/2014 | 9/9/2014 | 9/10/2014 | P | CANC |
Andy J. Long
|
|
|
inspection conducted on 9/10
|