Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberESC14-00878
StatusFinaled
Name JEFFREY A HANNES
Site Address 3201 W AIRPORT WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
This project will provide design solutions for the realignment of the existing angled segment of Taxiway K at the west end of Taxiway K, including the reconstruction of the intersection of Taxiways J, F, and K.

The extent of the Taxiway K realignment is understood to include the following area: Starting on Taxiway J at the south side of the UPS Apron; Extending to the intersection of Taxiways J, F, and K; and continuing southeast on Taxiway K to the east/west alignment of Taxiway K; a distance of approximately 1,000 feet and inclusive of the Taxiway J,F,and K intersection.

The scope of the work will require the realignment of Taxiway K to provide ADG IV taxiway abject free clearance from existing hangars on the west side of the taxiway and improve line of sight with the new Air Traffic Control Tower. Full-depth reconstruction in asphalt concrete is anticipated for both the taxiway and the taxiway shoulder. Grading and drainage improvements will be required, including the installation of underdrains and new drainage structures as necessary. New taxiway edge lights and signage will be required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection1/11/20161/11/20161/11/2016 PASS
DetailsAndy J. Long
Runway paving project complete and grading permit finaled. No trackout issues observed around airport perimeter. ESC permit finaled.
DOC - Permit Finaled1/11/20161/11/20161/11/2016PPASS
DetailsAndy J. Long
Aging Inspection11/9/201511/9/201511/9/2015 CANC
DetailsEvan Jenkins
Aging Inspection9/7/20159/7/20159/8/2015 PASS
DetailsAndy J. Long
WIP. No sediment runoff or fugitive dust leaving construction area within secured airport runway area.
General Inspection7/6/20157/6/20157/6/2015 PASS
DetailsAndy J. Long
Aging Inspection5/6/20155/6/20155/6/2015 PASS
DetailsEvan Jenkins
WIP: No ESC issues at this time
Aging Inspection3/6/20153/6/20153/6/2015 PASS
DetailsAndy J. Long
Some activity on runways occuring on south side of airport area. No trackout, dust, or offsite stockpiles in use. Site is self contained and in restricted area. No corrections.
Site Preparation9/22/20149/23/20149/23/2014APASS
DetailsAndy J. Long
Jeff Phone #: ###-####

Runway realignment project by Central Paving. Site is within restricted zone. Discussed ESC conditions and BMPs for site with Jeff. He stated inlets are in place, water supression for dust, and control trackout as necessary. Flat area, no surface water.

ESC fees paid. Approved.