Permit Information
Permit NumberESC14-00892
StatusFinaled
Name JIM CONGER
Site Address 2705 W MALAD ST
Project NameBella Vista/Hope Ridge Sub
Customer Number 
ePlanReviewNo
Description
Residential subdivision infill project. SWPPP with ESC site map submitted and approved. BMPs include: stabilized construction entrance (x2), regular street sweeping, no hazardous material storage allowed at site, lined concrete washout, perimeter wattles along south property line, and inlet protection on existing and new DIs. Site is mostly flat with a gentle slope downward to the east (towards Vista). Site has elected to apply for Low Erosivity Waiver instead of CGP eNOI for project (R Factor 4.72) - not listed as submitted to EPA at time of plan review.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final11/24/201512/1/201512/2/2015APASS
DetailsAndy J. Long
Work complete. No temp BMPs installed in MS4 on Malad. No remaining unstabilized area. Dumpsters and materials removed. All ESC permits finaled for townhome subdivision except ESC15-00267 to remove yellow signs, sweep interior road/gutter, and remove inlet bag.

No further ESC inspections on this permit.
DOC - Permit Finaled12/2/201512/2/201512/2/2015PPASS
DetailsAndy J. Long
Site Final11/20/201511/24/201511/24/2015ANR
DetailsAndy J. Long
Some minor interior work ongoing.

Need to remove yellow permit signs, dumpster trailer, sweep up, and remove DI bag on the south inlet.

Will check next week.
Site Final11/17/201511/20/201511/20/2015PNR
DetailsAndy J. Long
rescheduled
General Inspection11/2/201511/2/201511/2/2015 PASS
DetailsAndy J. Long
Near completion. Final trash and material haul off in progress. No trackout or discharges. Open space for townhome subdivision has been landscaped and stabilized. Will check for site final next week.
General Inspection8/31/20158/31/20158/31/2015 PASS
DetailsAndy J. Long
All townhomes in Bella Vista have been framed. WIP on the east 7 homes, whiles the 7 homes on the west are very near completion. Trash and materials have been recently cleaned. No vdischarges or spills observed. No corrections issued.
Aging Inspection6/30/20156/30/20156/30/2015 PART
DetailsAndy J. Long
Need to pick up trash and unused wood scraps. Sweep up sawdust and sediment in gutters.

Scheduling a conference with RP-GC Gary Olsen for tomorrow AM to discuss housekeeping that is needed.

No trackout or discharges offsite.
General Inspection4/29/20154/30/20154/30/2015APASS
DetailsAndy J. Long
Townhome construction in progress. First 7 foundations have been poured, a lined cement washout was properly used.

RP/GC Gary onsite. Once foundation work is complete on east side, they will move washout to SE corner in order to start on west side. Each townhome has seperate permit between (ESC15-00266 to 284)

No dust, trackout, or uncontained trash or materials. Very clean site, inlet protection is installed. Approved.
Aging Inspection4/1/20154/1/20154/1/2015 PASS
DetailsAndy J. Long
Townhome subdivision access road, utilities, and stormwater drainage system have been completed. Malad street is free of trackout and sediment in gutter.

No vertical construction has started yet. Once it starts, drop inlet protection should be provided on the private storm drain at south end of site.

No issues, no sediment runoff or fugitive dust..
Random Inspection1/30/20151/30/20151/30/2015PPASS
DetailsAndy J. Long
New street curbing on Malad is complete and has been swept and cleaned. Access road to the subdivsion is paved and site utilities and drainage are also installed. Currently no activity, but the site has been left clean and dirt in central area is below grade of curbing so works to contain runoff and sediment.

No corrections needed, approved.
Tracking Control10/22/201410/24/201410/24/2014APEND
DetailsAndy J. Long
Check to see that Malad Street has been swept. Supposed to be cleaned Thursday evening.

Malad Street appears to have been cleaned. There is no gutter or stormdrain on this portion Malad so the combination of puddles, ongoing rain, and utility trench work occurong there is still some trackout/mud on the street.

Will request frequent sweeping until better stabilization and perimeter control occurs.

No other issues.
Tracking Control10/22/201410/22/201410/22/2014PFAIL
DetailsAndy J. Long
Trackout to Malad Street caused by utility contractors. No perimeter controls; construction entrance is small and is muddy - workers not using designated entrance.

Verbal CN issued to RP Jim to sweep up road and install BMPs along Malad to prevent trackout and mud.

Waiting to hear back when corrections will be made.
Site Preparation9/22/20149/22/20149/22/2014PPASS
DetailsAndy J. Long
New infill sub in Vista neighborhood. Flat, low risk site with no MS4 infrastructure or surface water within 100 yards of project.

Construction entrance is installed and 1-2 foot vegetated buffer surrounds graded area. Sheet flow is to center of lot. Developer notified work would be last Friday which was approved. No trackout or dust issues at time of inspection.

Approved.