DOC - Permit Finaled | 3/13/2015 | 3/13/2015 | 3/13/2015 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 3/13/2015 | 3/13/2015 | 3/13/2015 | | PASS |
Andy J. Long
|
|
|
Restroom is installed, work trailer has been removed as well as straw wattle protecting swale.
Bark chip has been laid down in area that will soon be a new playground. Some small areas of bare ground are contained by grass. Irrigation lines have been put in by Parks n Rec.
GC Antonio confirmed work is complete and Parks has signed off. ESC permit conditions satisfied.
|
Random Inspection | 1/6/2015 | 1/6/2015 | 1/6/2015 | P | PASS |
Andy J. Long
|
|
|
Modular bathroom structure at Terry Day Park has been installed. Job trailer and wattles protecting drainage swale are still on site, which is currently inactive. The disturbed area needs landscaping or stabilization. No trackout or stormwater pollution sources found at site.
|
Site Preparation | 10/21/2014 | 10/22/2014 | 10/22/2014 | A | PASS |
Andy J. Long
|
|
|
Antonio ###-####. Early morning please
Terry Day park restroom grading and trenching project. Inspected site with RP/GC Antonio and discussed scope of project. Work will include trenchwork for utilities, grubbing/grading, and placing dirt on park property off Overland and tacifying.
Site is relatively flat, drainage swale has fiber watte perimeter protection, permit posted on job trailer, and construction access via stabilzed lane off Kootenai.
Approved for excavation.
|