Permit Information
Permit NumberESC14-00928
StatusFinaled
Name ROBERT FELDMANN
Site Address 119 S 10TH ST
Project Name10th and Grove Condos
Customer Number 
ePlanReviewNo
Description
119 Grove: To construct 4 floors, 26 units of stick built condominium spaces on top of a two story Concrete parking podium. The podium plans are currently under review as BLD14-02156.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final5/4/20175/5/20175/4/2017APASS
DetailsMelissa Jannusch
DI bags have been removed. Okay to final.
Aging Inspection4/18/20174/18/20174/18/2017 PEND
DetailsMelissa Jannusch
DI bags need to be removed on 11th and grove street before the ESC permit can be closed. They are currently clogged and causing stomwater to back up. Sent e-mail to applicant and RP requesting a date when the DI bags will be removed. No other corrections.
Aging Inspection2/15/20172/15/20172/15/2017 CANC
DetailsMelissa Jannusch
Site Final12/16/201612/16/201612/16/2016PNR
DetailsAndy J. Long
Need to remove DI bag on 11th and Grove
General Inspection10/18/201610/18/201610/18/2016PPASS
DetailsAndy J. Long
MS4 on 11th and Grove has filter bag installed and is draining and filtering. Runoff down Grove from site is not muddy or discolored. No corrections isssued
Aging Inspection9/20/20169/20/20169/21/2016 PART
DetailsAndy J. Long
Need to sweep up dirt & dust material within fenced area that encloses gutter on 10th street.

MS4 filter bag that recieves runoff from site is installed and in good condition.
General Inspection7/20/20167/22/20167/22/2016APASS
DetailsAndy J. Long
follow up BMP violation for sweeping/housekeeping

DI bag was changed out as requested. Sweep up in progress. Will check conditions early next week. Initial request has been addressed by RP. Approved.
BMP Violation7/18/20167/19/20167/20/2016AFAIL
DetailsAndy J. Long
Correction notice to sweep up loose cemetitious material and debris within the barricaded area on Grove and 10th.

Change DI bag on 11th Street and sweep gutter between project and DI that has residue.

Verbal CN to Mike with CSDI ###-####
General Inspection5/16/20165/16/20165/16/2016PPASS
DetailsAndy J. Long
WIP on exterior. Site perimeter is clean. No corrections issued.
Random Inspection4/20/20164/20/20164/20/2016PPASS
DetailsAndy J. Long
Building frame is complete. Site perimeter is free of trackout, loose sediment, and discharges. No corrections needed. Crew in progress of working on the exterior
Random Inspection3/25/20163/25/20163/25/2016PDONE
DetailsRex Boyles
random track out insp no track out looks clean
Aging Inspection2/24/20162/24/20162/24/2016 PASS
DetailsAndy J. Long
Vertical construction in progress. No trackout, discharges, or uncontained material from site. DI bags installed on surrounding MS4. Approved.
General Inspection12/4/201512/4/201512/4/2015PPASS
DetailsAndy J. Long
WIP on vertical construction. No trackout or discharges from site. Site perimeter is well kept. No corrections.
General Inspection9/30/20159/30/20159/30/2015PPASS
DetailsAndy J. Long
WIP on 10th & Grove condos (119 Grove). Site perimeter has some minor amounts of loose sediment and sand that should be swept. Trash and materials are contained. No discharges or runoff from site. No violations observed.

Note: Project related permit ESC14-00713 for the foundation and initial site work has been finaled.
Random Inspection8/25/20158/25/20158/25/2015PPASS
DetailsAndy J. Long
WIP on 10th and Grove Condos. Site grading and foundation construction is complete (covered under ESC14-00713).

No discharges or significant amounts of loose sediment leaving site. Stormdrain has inlet filter bag installed.