Site Final | 3/10/2017 | 3/10/2017 | 3/10/2017 | A | PASS |
Andy J. Long
|
|
|
Construction on both buildings complete and units are occupied. Parking lot and permanent stormwater system installed, common areas landscaped. No trash, loose materials on site. All temporary BMPs removed. ESC conditions satisfied.
|
General Inspection | 3/10/2017 | 3/10/2017 | 3/10/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/23/2017 | 1/23/2017 | 1/23/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/6/2016 | 12/6/2016 | 12/8/2016 | | PASS |
Andy J. Long
|
|
|
WIP on interior. Exterior complete, parking lot and landscaping installed. Construction staging area still in parking lot, trash contained but needs hauled away.
Note: DI on Opohonga has had filter bag already removed.
|
General Inspection | 10/21/2016 | 10/21/2016 | 10/21/2016 | | PASS |
Andy J. Long
|
|
|
WIP on interior of west building. No trackout or discharges observed. Trash is contained and parking lot is relatively clean. Approved
|
General Inspection | 9/5/2016 | 9/5/2016 | 9/6/2016 | | PASS |
Andy J. Long
|
|
|
Interior work ongoing, parking lot is paved. No trackout, uncontained trash or other construction materials leaving the construction site. MS4 on street has inlet filter bag installed. Approved.
|
General Inspection | 7/19/2016 | 7/19/2016 | 7/19/2016 | | PASS |
Andy J. Long
|
|
|
Vertical construction and interior work in progress. Parking area is paved, storm drains have sediment protection. No trackout or discharges.
|
General Inspection | 6/3/2016 | 6/3/2016 | 6/3/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: no issues observed. no discharges leaving site
|
General Inspection | 4/18/2016 | 4/18/2016 | 4/18/2016 | | PASS |
Andy J. Long
|
|
|
Vertical construction now in progress. Parkling lot asphalt has been installed.
No trackout, trash containers provided, and MS4 on Opohonga has inlet protection. No corrections requested
|
General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 | | PASS |
Andy J. Long
|
|
|
WIP on finishing foundations for the two 28 plex buildings. No significant trackout, DI bag on MS4 on Opohonga is installed and has filtering capacity. Utility line not yet patched in street.
Provided both RPs Pat and Jeremy, who were on site a new yellow ESC sign to post.
Approved.
|
General Inspection | 1/15/2016 | 1/15/2016 | 1/15/2016 | | PART |
Andy J. Long
|
|
|
No activity. No permit sign.
Need to post sign and install BMPs to prepare for further construction (construction entrance)
|
General Inspection | 11/30/2015 | 11/30/2015 | 11/30/2015 | | FAIL |
Andy J. Long
|
|
|
Curb work suspended due to freezing temperature and inability to pour concrete. Significant amount of loose sediment and sand has been left in roadway. No construction entrance provided. No activity at time of inspection. No discharge or polluted storm water flows.
Correction request to Biltmore Company to sweep up roadway with sweeper when curbing is complete and to manual sweep in front of site prior to curb completion.
|
General Inspection | 10/13/2015 | 10/13/2015 | 10/13/2015 | | PASS |
Evan Jenkins
|
|
|
|