Site Final | 7/9/2015 | 7/9/2015 | 7/9/2015 | A | PASS |
Andy J. Long
|
|
|
Sidewalk and street lamp installation is complete and site has been cleaned of materials and waste from project.
Drop inlet bags to remain for future development.
ESC permit conditions satisfied. Permit closed.
|
General Inspection | 6/16/2015 | 6/16/2015 | 6/16/2015 | | PASS |
Evan Jenkins
|
|
|
No Issues at this time
|
General Inspection | 5/1/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Andy J. Long
|
|
|
Workers in process of pouring the new sidewalks from Marianne Williams Park to Parkcenter Blvd.
No discharges or runoff off to stormdrains. 5 concrete washouts bins are being utilized, 3 of which are full. May need service to contain remaining work to be done.
A-core working on curb cutting. Will need to have sweeper pick up concrete dust and prevent slurry runoff to DIs.
|
General Inspection | 4/6/2015 | 4/6/2015 | 4/6/2015 | A | PASS |
Andy J. Long
|
|
|
Work on sidewalk along Barber Valley (road to M. Williams Park) has resumed. Inlets along Barber Vally have DI protection. Stockpiles stored on flat open area with limited runoff potential. No trackout or discharges. Cement work has not yet started, but will need to make sure they have concrete washout on site due to wetlands and high groundwater level in area. Verbal request issued to RP.
|
General Inspection | 3/4/2015 | 3/4/2015 | 3/4/2015 | P | PASS |
Andy J. Long
|
|
|
Sidewalk project in Barber Station/Marianne Williams park area is still inactive. Site has BMPs in place (DI protection) and materials for installation have been removed until project resumes. No corrections needed at this time.
|
Random Inspection | 1/28/2015 | 1/28/2015 | 1/28/2015 | P | PASS |
Andy J. Long
|
|
|
Barber Station sidewalk project is still on winter shut down. Site is clean. No issues. Permit will become active as activity resumes.
|
General Inspection | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Andy J. Long
|
|
|
Sidewalk project for new Barber Valley townhome sub is temporarily suspended due to the cold weather and inability to pour concrete. No issues at site, RP called to inform me of status and alert that site prep (fencing and BMP installation, equipment staging) is beginning to occur for the townhomes and a site prep will be conducted for ESC14-01083 will be sheduled later this week. Approved.
|