Permit Information
Permit NumberESC14-01033
StatusFinaled
Name LANCE SNYDER
Site Address 2357 S FIVE MILE RD
Project Name2357 South Five Mile
Customer Number 
ePlanReviewNo
Description
As per ESC conditions, Construct a single family residence on this building lot
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection9/15/20159/15/20159/15/2015 PASS
DetailsEvan Jenkins
DOC - Permit Finaled9/15/20159/15/20159/15/2015PPASS
DetailsEvan Jenkins
Project Complete
ESC Conditions Satisfied
Aging Inspection7/15/20157/15/20157/15/2015 PASS
DetailsAndy J. Long
Aging Inspection5/15/20155/15/20155/15/2015 PASS
DetailsAndy J. Long
Home is complete. Landscaping and tree installation in progress. No more grading needed. No trackout or sediment runoff during rain event. Will close when stabilzed.
Complaint Inspection3/11/20153/11/20153/11/2015APEND
DetailsAndy J. Long
Report received of stockpiling and general mess making in the sidewalk & gutter.

Site is currently being landscapers. Workers had piled dirt on sidewalk to build berm. Upon arrival berm was mostly complete and 3 workers were sweeping up the sidewalk and gutter.

No trackout or discharges occuring, drop inlet on Five Miles has sediment protection. Will check back to make sure site has been well as the landscaping is completed.
BMP Violation12/18/201412/19/201412/19/2014PPART
DetailsEvan Jenkins
Permit Posted, Drop Inlets are protected.
Still needs sweeping and construction entrance installed. Will follow up monday
BMP Violation12/17/201412/18/201412/18/2014PPART
DetailsEvan Jenkins
Permit has been posted, and sweeping occured on the approach. Jim stated the owner is schedualing for street sweeping and installation of construction entrance. I disclosed that if the rest of the corrections arent corrected by midday, SWO will be issued until all corrections have been addressed/fixed
BMP Violation12/16/201412/17/201412/17/2014PFAIL
DetailsEvan Jenkins
Corrections haven't been completed. Contacted Jim via cell to disclose issues need to be fixed by Tomorrow afternoon 12-18-14 or SWO will be issued until corrections have been made. Jim agreed and stated he will
Tracking Control12/16/201412/16/201412/16/2014PFAIL
DetailsEvan Jenkins
Significant Trackout from site onto 5 Mile Road. Called RP Lance and left VM describing Violations and for him to contact me back.
Corrections:
1.) Install Construction Entrance/Exit
2.) Sweep 5 Mile Road and Entry
3.) Install Drop Inlet Protection
4.) Post Permit onsite in visible area
Schedualed a BMP Violation inspection for tomorrow afternoon 12-17-14 to follow up to see if any effort has been performed to address violations
Site Preparation12/1/201412/1/201412/1/2014PPASS
DetailsAndy J. Long
Jim Phone #: ###-####

Site ready for excavation. New infill lots on flat terrain and no surface water on or adjacent to site. Once utility lines are installed, contractor will provide vehicle tracking pad for sub-contractors since there is no on-street parking on Fivemile.

Permit posted. BMPs will be sediment control for trackout and general housekeeping. Approved.