DOC - Permit Finaled | 6/19/2015 | 6/19/2015 | 6/19/2015 | P | PASS |
Andy J. Long
|
|
|
Site final and document final. 3 new Harris Crossing townhomes are now complete and stabilized. ESC conditions satisfied.
|
Aging Inspection | 6/4/2015 | 6/4/2015 | 6/4/2015 | | PASS |
Evan Jenkins
|
|
|
No Issues at this time
|
Site Preparation | 1/6/2015 | 1/6/2015 | 1/6/2015 | A | PASS |
Andy J. Long
|
|
|
Phone #: ###-#### Inspection requested via web by Austin Wagner
Parcel is adjacent to the two projects started yesterday and the houses will be aligned 3 in a row back from street. BMPs installed. Permit posted. Excavator did pretty good to minimize trackout in yesterday's work. Approved.
|