Site Final | 9/19/2016 | 9/26/2016 | 9/28/2016 | P | PASS |
Andy J. Long
|
|
|
Check for DI bag removal requested 9/19g
Home complete, landscaped, and occupied. Temp BMP DI bag on Locust and Franklin removed last week as requested. ESC conditions satisfied.
|
Aging Inspection | 9/19/2016 | 9/19/2016 | 9/19/2016 | | PART |
Andy J. Long
|
|
|
Temporary BMP installed was not removed once homes were complete and landscaped as required by permit.
Request issued to TBL construction to remove DI bag and permit sign from site. Site final scheduled for 9/26, contractor Tim says it shall be removed.
|
Aging Inspection | 7/18/2016 | 7/18/2016 | 7/18/2016 | | PASS |
Andy J. Long
|
|
|
Final landscaping in progress. No violations.
|
Aging Inspection | 5/16/2016 | 5/16/2016 | 5/16/2016 | | PASS |
Andy J. Long
|
|
|
WIP.. DI on corner has sediment filter bag installled. No trackuot, yard is landscaped but some site improvements still occuring.1205 Franklin also in progress. No corrections issued.
Will need to remove DI BMP when complete.
|
Aging Inspection | 3/14/2016 | 3/14/2016 | 3/14/2016 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 1/11/2016 | 1/11/2016 | 1/12/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Locust and Franklin Street are clean. Storm drain on corner has sediment mat installed. No violations observed. Approved.
|
Aging Inspection | 11/9/2015 | 11/9/2015 | 11/9/2015 | | CANC |
Evan Jenkins
|
|
|
|
Aging Inspection | 9/8/2015 | 9/8/2015 | 9/8/2015 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 7/9/2015 | 7/9/2015 | 7/9/2015 | | PART |
Andy J. Long
|
|
|
Access to site has been restricted to prevent trackout from future driveway area. Perimeters of site are clean, but the street does not have gutters so there are some muddy puddles along Franklin.
Correction:
Install BMP to protect storm drain on Franklin and Locust.
|
Random Inspection | 5/6/2015 | 5/6/2015 | 5/6/2015 | P | PASS |
Andy J. Long
|
|
|
Frame in progress. Permit posted. Site surrounded by chain linking fencing. Sidewalk vegetation along Locust has been preserved. No trackout or discharges. Approved.
|
Site Preparation | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PART |
Andy J. Long
|
|
|
WIP. DI protection, concrete washout, and permit posting has been provided. Digging a large basement so will need to sweep up trackout when they backfill/haul off excess dirt.
No perimeter protection BMPs for all the dirt dug for basement and storm predicted for weekend. Will discuss with RP and reinspect. Currently no discharges or sediment leaving site, but could be a problem.
|