General Inspection | 6/8/2016 | 6/8/2016 | 6/8/2016 | | PASS |
Andy J. Long
|
|
|
Home complete, landscaped and occupied. DI bag to remain until home next door is done. No further ESC requests. Permit finaled.
|
DOC - Permit Finaled | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/24/2016 | 5/24/2016 | 5/24/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 5/9/2016 | 5/9/2016 | 5/9/2016 | | PEND |
Evan Jenkins
|
|
|
re-veg
|
General Inspection | 4/22/2016 | 4/22/2016 | 4/22/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/7/2016 | 4/7/2016 | 4/7/2016 | | PASS |
Andy J. Long
|
|
|
Home complete and occupied. Yard getting final landscaping. Eroded bank in yard has been raked out and hydroseed applied. Will watching for revegetation and removal of the DI bag on Windsong
|
General Inspection | 3/23/2016 | 3/23/2016 | 3/23/2016 | | PASS |
Andy J. Long
|
|
|
landscaping in progress
|
General Inspection | 3/8/2016 | 3/8/2016 | 3/8/2016 | | PASS |
Andy J. Long
|
|
|
Landscaping in progress. No trackout or discharges.
|
General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 2/5/2016 | 2/5/2016 | 2/5/2016 | | PASS |
Andy J. Long
|
|
|
In process of landscaping the backyard. No trackout or breaches in the vegetation buffer around the bottom of the site. Approved.
|
General Inspection | 1/21/2016 | 1/21/2016 | 1/22/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/6/2016 | 1/6/2016 | 1/6/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/22/2015 | 12/22/2015 | 12/22/2015 | | PART |
Andy J. Long
|
|
|
No activity at time of inspection. No windblown trash issues, trackout, or illegal parking on culdesac.
Backyard hillside has some erosion rills developing and sediment depositing in the preserved vegetation below grading. No runoff exiting site, but will need to be fixed and assessed for improvements once conditions improve.
|
Site Preparation | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | CANC |
Andy J. Long
|
|
|
data entry error
|
General Inspection | 12/3/2015 | 12/3/2015 | 12/3/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled for 12/4
|
General Inspection | 11/18/2015 | 11/18/2015 | 11/18/2015 | | PASS |
Andy J. Long
|
|
|
Home near completion. Trash container has been serviced recently, no debris or material around site. No significant trackout, no erosion occuring on graded hillside yard area. No corrections.
|
Complaint Inspection | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | PEND |
Andy J. Long
|
|
|
Complaint regarding windblown trash on culdesac received at permit desk.
Verbal correction request to schedule trash removal and to cover/secure existing trash. Very windy day making situation worse.
GC was onsite making corrections and securing light weight trash. Pick up is scheduled and was not order today due to high winds blowing the fines in the bottom of the container upon emptying.
Will check back to inspect conditions...
|
General Inspection | 10/22/2015 | 10/22/2015 | 10/22/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/7/2015 | 10/7/2015 | 10/7/2015 | | PASS |
Andy J. Long
|
|
|
WIP. No sediment runoff or trackout from site. Recent issues regarding wind blown trash have been resolved.
No corrections at this time.
|
Complaint Inspection | 9/22/2015 | 9/22/2015 | 9/22/2015 | P | PART |
Andy J. Long
|
|
|
Corrections needed:
1. Pick up materials no longer needed (waste). Insulation foam across street as well 2. Sweep driveway apron and culdesac in front of home.
|
General Inspection | 9/17/2015 | 9/17/2015 | 9/17/2015 | | PASS |
Andy J. Long
|
|
|
Home near completion. No activity at time of construction. The recently graded back yard that had slopes compacted and tracked did not suffer any rill or gully erosion during the afternoon's rain storm. No sediment runoff observed.
|
Site Preparation | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | PEND |
Andy J. Long
|
|
|
note: not a site prep inspection, data entry error
Corrective actions in progress to fix grading. Vegetative perimeter buffer has remained undisturbed. No discharges or sediment runoff at time of inspection
|
General Inspection | 9/1/2015 | 9/1/2015 | 9/1/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
Conference | 9/1/2015 | 9/1/2015 | 9/1/2015 | P | PEND |
Evan Jenkins
|
|
|
Meeting onsite to discuss Bruno Built, Inc grading onto adjacent property and stockpiling. Met with owner, builder, Jason Taylor, Jim Willey and myself. Bruno to remove dirt and rocks from nieghbors property or stop work order shall be issued. Jason Taylor to work with Bruno to get issues resolved soon. Will follow up
|
General Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/29/2015 | 7/29/2015 | 7/29/2015 | | PASS |
Evan Jenkins
|
|
|
Currently prepping landscaping. No real issues at this time
|
General Inspection | 7/14/2015 | 7/14/2015 | 7/14/2015 | | PASS |
Andy J. Long
|
|
|
WIP on frame and interior. No silt fence due to vegetated buffer. No sediment leaving site, no hillside rills or gullys observed. Permit posted on porta-pot. No corrections.
|
Conference | 5/15/2015 | 5/15/2015 | 5/15/2015 | P | PASS |
Andy J. Long
|
|
|
Permit sign posted. No activity occuring during the rain. No muddy runoff from site. Preservation of perimeter vegetation has around area of disturance have kept sediment on site. NO trackout, trash is contained. Approved.
|
Site Preparation | 3/26/2015 | 3/26/2015 | 3/26/2015 | P | FAIL |
Andy J. Long
|
|
|
No site prep inspection requested by Bruno Built.
Permit is not posted.
Washout pit and construction entrance installed. Downslope BMP is preservation of existing vegetation.
|