DOC - Permit Finaled | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PASS |
Andy J. Long
|
|
|
All framing is complete. Landscaping and exterior painting in progress. No further ESC inspections on this permit. Main Asheville permit ESC14-01052 and for carports ESC15-01471;open for final clean up and temp BMP removal. No violations at time of inspection.
|
General Inspection | 3/3/2016 | 3/3/2016 | 3/3/2016 | | PASS |
Evan Jenkins
|
|
|
landscaping in progress
|
General Inspection | 2/17/2016 | 2/17/2016 | 2/17/2016 | | PASS |
Rock A. Hudson
|
|
|
Minor dirt on parking areas due to landscape work. No major issues
|
General Inspection | 2/2/2016 | 2/2/2016 | 2/2/2016 | | PASS |
Evan Jenkins
|
|
|
wip: no issues observed at this time
|
General Inspection | 1/18/2016 | 1/18/2016 | 1/19/2016 | | CANC |
Andy J. Long
|
|
|
corrections in progress under full site permit for Ashville Commons, see ESC14-01052 for details. No inspection at this time.
|
General Inspection | 1/1/2016 | 1/1/2016 | 1/6/2016 | | PASS |
Jim Little
|
|
|
Landscaping has begun, many buildings completed, thrash being contained for the most part, no major issues.
|
General Inspection | 12/17/2015 | 12/17/2015 | 12/17/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 12/2/2015 | 12/2/2015 | 12/3/2015 | | PASS |
Jim Little
|
|
|
no major issue's
|
General Inspection | 11/17/2015 | 11/17/2015 | 11/17/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/2/2015 | 11/2/2015 | 11/2/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/16/2015 | 10/16/2015 | 10/16/2015 | | PASS |
Evan Jenkins
|
|
|
No ESC issues at this time
|
General Inspection | 10/1/2015 | 10/1/2015 | 10/1/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: on all 4-plexes. SIlt fence still in place along canal on east side of project. Lots of building materials staged in parking areas, due to tight space
|
General Inspection | 9/16/2015 | 9/16/2015 | 9/16/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 9/1/2015 | 9/1/2015 | 9/1/2015 | | PASS |
Andy J. Long
|
|
|
WIP on foundations and frames at Asheville Commons. Perimeter silt fence in good condtion. No trackout or fugitive dust. Concrete washout provided for cement/concrete work.
Approved.
|
General Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | | CANC |
Andy J. Long
|
|
|
Asheville Commons apartment subdivision inspected Thursday 8/13; no violations. No inspection today
|
General Inspection | 7/29/2015 | 7/29/2015 | 7/29/2015 | | PASS |
Andy J. Long
|
|
|
Vertical work on apartment unit has not yet started, so flat work in progress. Asheville Commos road and utility work is currently under construction. See ESC14-01052
|
General Inspection | 7/14/2015 | 7/14/2015 | 7/14/2015 | | PART |
Andy J. Long
|
|
|
No activity on apartment units at Asheville Commons. Infrastructure and utilities currently in progress. Some trackout on to Maple Grove, no construction entrance - see ESC14-01052 for corrections.
|