Permit Information
Permit NumberESC15-00082
StatusFinaled
Name JEREMY AMAR
Site Address 826 N MAPLE GROVE RD
Project NameAshville Commons
Customer Number 
ePlanReviewNo
Description
Bldg N (14) -Type 3 (Elev 3, A-203): Multifamily 4-Plex project consisting of 14 two-story buildings on 3.79 acre site located at 826 N Maple Grove, just north of Emerald. 13 buildings (52 units) will be 2 bedroom, 2 bathroom and 1 building (4 units) will be 1 bedroom, 1 bathroom.

Of the 13, 2 bedroom buildings, the two buildings located adjacent to Maple Grove have a different rear elevation and roof line and are designated as Building Type 3 while the other 2 bedroom buildings are Building Type 1. The 1 bedroom building is designated as Building Type 2.

Since all 14 buildings will be on the same parcel, they will all share the 826 N Maple Grove address. We propose to individually identify each building with a letter (A thru N) as shown on the site plan A-101. Within the plans, the buildings also have a number designation (1 thru 14) for plan referencing.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled3/7/20163/7/20163/7/2016PPASS
DetailsAndy J. Long
All framing is complete. Landscaping and exterior painting in progress. No further ESC inspections on this permit. Main Asheville permit ESC14-01052 and for carports ESC15-01471;open for final clean up and temp BMP removal. No violations at time of inspection.
DOC - Permit Finaled1/25/20161/25/20161/25/2016PDONE
DetailsAndy J. Long
4-plex complete. See ESC14-01052 for ongoing construction. No more inspections on this permit.
General Inspection12/11/201512/11/201512/11/2015 CANC
DetailsAndy J. Long
General Inspection10/26/201510/26/201510/26/2015 PASS
DetailsAndy J. Long
WIP on 4-plexes. Site perimeter has sediment containment with silt fencing and curbing/sidewalks. Parking and access drive is paved with stormwater facilities installed. No offsite runoff or trackout. Approved.
General Inspection9/8/20159/8/20159/8/2015 CANC
DetailsAndy J. Long
General Inspection7/17/20157/17/20157/17/2015 PASS
DetailsEvan Jenkins