Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberESC15-00180
StatusFinaled
Name BOB GOODWIN
Site Address 3050 S SHOSHONE ST
Project NameBoise Holiday Inn Express & Su
Customer Number 
ePlanReviewNo
Description
4 story hotel (HOLIDAY INN EXPRESS & SUITES) Construct a new 4 story hotel building and related site improvments.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/10/201610/11/201610/13/2016PPASS
DetailsAndy J. Long
All temporary BMPs have been removed. NO filter bags left on MS4 on Sunrise Rim or Shosone. Site is landscaped, stabilized, and perimeter gutters were swept. ESC permit conditions satisfied.
General Inspection10/7/201610/7/201610/10/2016 CANC
DetailsAndy J. Long
Site Final8/18/20168/22/20168/22/2016APEND
DetailsAndy J. Long
Site Final8/11/20168/18/20168/18/2016APEND
DetailsAndy J. Long
Site Final8/11/20168/11/20168/11/2016ANR
DetailsAndy J. Long
Finishing touches in progress, very close to completion.

To get ESC final:

-complete final clean up of construction equipment and and any loose materials including sediment
- clean any dirt or mud in gutters on Sunrise Rim and Shoshone
- remove and dispose of all sediment filter bags on Sunrise Rim and Shoshone and at parking lot entrances..
- Call in for Site Final when above requests are complete ###-####
General Inspection7/8/20167/8/20167/8/2016PPASS
DetailsTroy Cobbley
Everything looks fine. The fire sprinkler contractor had a water leak on their underground supply line.
General Inspection6/28/20166/28/20166/28/2016 PASS
DetailsAndy J. Long
WIP on interior and workers broom sweeping parking lot to clear landscaping dirt and loose debris around dumpster. No trackout or discharges. No corrections at this time.

Note: associated ESC permit issued with GRD permit has been finaled (ESC15-00822)
General Inspection5/13/20165/13/20165/13/2016APASS
DetailsBob Reichert
looked ok
General Inspection4/19/20164/19/20164/19/2016 PASS
DetailsEvan Jenkins
WIP: no esc issues observed at this time
General Inspection3/4/20163/4/20163/7/2016 PASS
DetailsAndy J. Long
WIP on interior. Parking lot and landscaping already complete. No significant trackout, no discharges. Will need to check MS4 DI sediment control bags for maintentance.
General Inspection1/18/20161/18/20161/19/2016 PASS
DetailsAndy J. Long
WIP. No trackout or discharges from Holiday Inn Express site. Parking lot is paved and vertical construction is in progress.

No materials currently staged on open lot on Elder that was being used by site. Contractor told me a trucking company uses this lot and is the source of trackout. No significant trackout at time of inspection. Will continue to monitor....
General Inspection12/1/201512/1/201512/2/2015 PART
DetailsAndy J. Long
Site is mostly stabilized minus the hotel building footprint. Vertical construction and framing are in progress.

Verbal correction to RP Bob to have street sweeper on Pasadena now that trenching and landscaping are complete. Significant amount of loose dirt in roadway and gutter.

Reqeusted that sweeping be conducted Thursday or Friday. Will check back early next week. See also ESC-00822.
General Inspection10/13/201510/13/201510/13/2015 PASS
DetailsAndy J. Long
WIP. Some minor trackout due to active curbing and road work. Sweep up will be after completion and paving. No fugitive dust observed or complaints received. No offsite discharges, uncontained trash, or loose sediment leaving site. Most of the distrubed area is surrounded by cement curbing. No corrections issued.
General Inspection8/26/20158/26/20158/26/2015 PART
DetailsAndy J. Long
Site prep inspection conducted with site pre-grading/grubbing on ESC15-00822. No significant trackout or loose sediment leaving site at new Holiday Inn, but very few BMPs installed around site. It is flat with limited MS4 infrastructure surrounding area.

Need to install constrution entrance and some more significant perimeter controls. Will schedule meeting with RP Bob to discuss what controls are need. Permit information located in job trailer.