Permit Information
Permit NumberESC15-00266
StatusFinaled
Name GARY OLSON
Site Address 2651 W MALAD ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Per the attached ESC conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/13/201510/13/201510/13/2015PPASS
DetailsAndy J. Long
Townhome complete. Materials staged in access alley have been swept and cleaned. All work on east side (7 townhomes) of Hope Ridge is complete. Interior work ongoing on west side of block and ESC permits open. ESC permi finaled.
Aging Inspection10/6/201510/6/201510/6/2015 PASS
DetailsAndy J. Long
WIP on interior woodwork, finishes and appliance installations. Trash container bins still on site. All landscaping and site paving is complete. No violations observed.
BMP Violation8/3/20158/3/20158/3/2015APART
DetailsAndy J. Long
BMP Violation7/29/20157/30/20157/30/2015APEND
DetailsAndy J. Long
CN issued by Code enforcement to clean up uncontained trash and building debris.

Re-iterated to RP-GC about BLD and ESC permit conditions to contain trash and debris. Site must be cleaned and all materials hauled away, swept up, and remaining waste in trash bins.

Stated to RP that site will be issued SWO on Monday August 3 if site is not cleaned and in compliance.

BMP Violation7/9/20157/9/20157/9/2015PPART
DetailsAndy J. Long
Significant amount of trash has been picked up and contained at site. Now trash container needs to be emptied. Alley ways have been swept but there is still a lot of debris on roadway.

Corrections:
-continue pick up of wood scraps and other debris.
- provide additional waste bin(s)
- sweep roads

Will set up follow-up inspection for next week
BMP Violation6/30/20157/1/20157/1/2015AFAIL
DetailsAndy J. Long
Housekeeping and trash clean up are needed ASAP

Uncontained trash and debris throughout site.

Correction request phoned in to RP/GC Gary

1. Collect all building and worker related trash around site include windblown litter.
2. Sweep up dust (dirt, wallboard, sawdust) and dispose properly
3. Have all trash containers emptied/serviced
General Inspection4/30/20154/30/20154/30/2015PPASS
DetailsAndy J. Long
Townhome foundation in progress in Bella Vista. BMPs installed, no violations at site. RP/GC is on site. DIs protected. First phase of 7 homes has completed foundations. Cement washout used and liquid is drying. No spills.

Requested that trash container be on site once vertical construction begins. No corrections needed.
Site Preparation4/9/20154/14/20154/14/2015APASS
DetailsAndy J. Long
Gary Phone #: ###-####


Bella Vista townhome project on Malad Street. 14 townhomes, 7 on each side of the newly developed square/block.

ESC permit issued for each BLD permit per townhome.

BMPs include permit signage, DI protection on subdivision storm drain and new inlet on Malad (west) of construction. Concrete washout pit has been excavated. RP Gary will line with visqueen on Wednesday. Concrete work will be Thursday or Friday.

The project will be phased - 7 homes on the east side will have their foundations started. Once in progress, the 7 other townhomes will have the foundations poured.

Discussed other BMPs that will be necessary including trash enclosures, trackout sweep up, stockpile control/placement, and having workers park on paved surfaces.

Approved to start to relocate misplaced sewer stub line. Subdivision ESC permit is ESC14-00892