Site Final | 12/2/2015 | 12/16/2015 | 12/17/2015 | P | PASS |
Andy J. Long
|
|
|
Permit signs removed from fence. Permanent stormwater infrastructure installed. Temporary DI bag removed. Common areas landscaped and parking lot paved and mostly swept. No trackout, no stockpiles or loose materials. No further ESC inspections necessary.
|
Site Final | 12/2/2015 | 12/2/2015 | 12/2/2015 | P | PEND |
Andy J. Long
|
|
|
Verbal request to RP Gary: -remove yellow ESC signs - sweep up loose dirt and debris in the west gutter -remove DI bag on inlet at south side of block
No violations at site, just need the above corrections to meet site final conditions. Note that all other ESC permits for Hope Ridge are closed except this one.
|
Aging Inspection | 11/24/2015 | 11/24/2015 | 11/24/2015 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 9/22/2015 | 9/22/2015 | 9/22/2015 | | PASS |
Andy J. Long
|
|
|
Near completion. Site is landscaped but requires final clean up and material haul off. No corrections issued
|
Site Preparation | 4/9/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Andy J. Long
|
|
|
Gary Phone #: ###-####
Bella Vista townhome project on Malad Street. 14 townhomes, 7 on each side of the newly developed square/block.
ESC permit issued for each BLD permit per townhome.
BMPs include permit signage, DI protection on subdivision storm drain and new inlet on Malad (west) of construction. Concrete washout pit has been excavated. RP Gary will line with visqueen on Wednesday. Concrete work will be Thursday or Friday.
The project will be phased - 7 homes on the east side will have their foundations started. Once in progress, the 7 other townhomes will have the foundations poured.
Discussed other BMPs that will be necessary including trash enclosures, trackout sweep up, stockpile control/placement, and having workers park on paved surfaces.
Approved to start to relocate misplaced sewer stub line. Subdivision ESC permit is ESC14-00892
|