Site Final | 12/4/2015 | 12/4/2015 | 12/4/2015 | P | PASS |
Andy J. Long
|
|
|
Work complete. No construction materials or loose sediment remaining on site. ESC permit conditions satisfied.
Note - previous inspection logged in error and was intended fro 920 Houston (ESC15-00006), which is still active.
|
General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 | | PART |
Andy J. Long
|
|
|
Pool is installed and landscaping and site work around pool is in progress. There is some trackout from active hauling of dirt with a bobcat.
Verbal correction issued to Visser construction contractor to make sure crews sweep up mud clud and loose dirt on roadway and to install sand bag check dam at west edge of property line to trap silts. The DI that drains the street is currently clogged
|
General Inspection | 11/10/2015 | 11/10/2015 | 11/10/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/23/2015 | 10/23/2015 | 10/23/2015 | | PASS |
Andy J. Long
|
|
|
WIP. No sediment trackout or housekeeping violations at site.
|
General Inspection | 10/8/2015 | 10/8/2015 | 10/8/2015 | | PASS |
Andy J. Long
|
|
|
WIP on site grounds. Home construction is complete on exterior, working on interior. No discharges, trackout or other issues at site. No corrections.
|
General Inspection | 9/23/2015 | 9/23/2015 | 9/23/2015 | | PASS |
Andy J. Long
|
|
|
WIP on mansion grounds and interior work. Site is keeping pretty clean, no complaints have been received. No significant trackout from site to Houston Road. Loose sediment in front of project should be swept as well as the trash should be serviced by end of the week. No violations, just general housekeeping is needed.
|
Site Preparation | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | NR |
Andy J. Long
|
|
|
Jeremy Phone #: ###-####
Site grading plans still need to be released/picked up. Work not scheduled to start till next week. RP Jeremy will call to schedule site prep
|