General Inspection | 10/23/2015 | 10/23/2015 | 10/23/2015 | | PASS |
Andy J. Long
|
|
|
|
Site Final | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Andy J. Long
|
|
|
Home construction complete. Yard is landscaped & stabilized and home is occupied. Surrounding hillside vegetation has been preserved. No ESC issues, hillside bond issued.
|
General Inspection | 10/8/2015 | 10/8/2015 | 10/9/2015 | | PASS |
Andy J. Long
|
|
|
BLD permits finaled. Yard is landscaped. Will continue to monitor perimeter hillside vegetation growth and check for any rills associated with irrigation or stormwater runoff.
|
General Inspection | 9/23/2015 | 9/23/2015 | 9/23/2015 | | PASS |
Andy J. Long
|
|
|
Frame and footprint of foothills home is complete and all utilities, including roof top stormwater stub is complete so there should be no more significant earthwork. No sediment leaving site, and work has stayed within clearing limits to preserve native vegetation and rock formations. No corrections, WIP
|
General Inspection | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation. Backfill is kept with limits of disturbance and vegetation down slope has been carefully preserved to act as natural sediment control. Permit is posted. Culdesac is free of trackout. Approved.
|
Site Preparation | 4/23/2015 | 4/23/2015 | 4/23/2015 | P | PART |
Evan Jenkins
|
|
|
Brian Phone #: ###-####
Permit Posted, construction entrance installed. Site is heavily vegetated. Issue: Excavation had begun prior to Site Prep Inspection Approval
|