Site Final | 10/21/2015 | 10/23/2015 | 10/23/2015 | A | PASS |
Andy J. Long
|
|
|
Home complete. Streets have been cleaned, but ongoing work with some trackout will continue to be monitored on open permits in River Heights #6. The yard is landscaped and stabilized. All permits finaled.
|
Aging Inspection | 10/21/2015 | 10/21/2015 | 10/21/2015 | | PART |
Andy J. Long
|
|
|
Sweep up on Signal Rock in progress. Construction is complete but streets are dirty. Currently in process of being cleaned. Will check back Friday for site final.
|
Site Preparation | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PASS |
Andy J. Long
|
|
|
###-#### Inspection requested via web by Erby Gonzales
|
Site Preparation | 5/12/2015 | 5/13/2015 | 5/13/2015 | A | PASS |
Andy J. Long
|
|
|
Phone #: ###-#### Inspection requested via web by Erby Gonzales
Permit signs posted. Drop inlets protected. First 4 homes to start in River Heights #6. Excavation to start today. Cement work next week. RP Erbie on site to discuss.
Designated lined washout will installed this week at culdesac on Playwright. Approved
|