DOC - Permit Finaled | 8/11/2016 | 8/11/2016 | 8/11/2016 | P | PASS |
Andy J. Long
|
|
|
ESC inspection activity covered under main site permit for Kensington, see ESC15-00504. This is a no fee permit
|
General Inspection | 7/18/2016 | 7/18/2016 | 7/18/2016 | | PASS |
Evan Jenkins
|
|
|
work in progress. no discharges leaving the site at this time
|
General Inspection | 5/31/2016 | 5/31/2016 | 5/31/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 4/15/2016 | 4/15/2016 | 4/15/2016 | | PART |
Evan Jenkins
|
|
|
Work Continues. Saxton Dr. needs to be swept. Called RP Barry to disclose track out issues and left VM. WIll follow up monday.
|
General Inspection | 2/29/2016 | 2/29/2016 | 2/29/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 | | PART |
Evan Jenkins
|
|
|
Trackout onto Saxton needs swept
|
Site Preparation | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Andy J. Long
|
|
|
Barry Phone #: ###-####
Approved for construction. Concrete to be poured weather permitting next week. Central designated concrete washouts provided. RP Barry with Bach Homes will add angular rock to construction entrance(s). DI bags on Gary and Saxton are installed. Will install additional control on south side of Saxton . Approved. See also main site ESC permit ESC15-00504. 6 of the individual building unit ESC permits are now issued. There is a total of 31.
|