Site Final | 4/17/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 4/14/2017 | 4/14/2017 | 4/17/2017 | | PASS |
Melissa Jannusch
|
|
|
Project is complete. Soil is stable. Okay to final.
|
General Inspection | 2/27/2017 | 2/27/2017 | 3/1/2017 | | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 1/10/2017 | 1/10/2017 | 1/11/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2016 | 11/25/2016 | 11/25/2016 | A | PART |
Andy J. Long
|
|
|
WIP on sidewalk and shoulder improvements. Structure for warehouse is erected and parking area is paved. NO discharges or fugitive dust observed. Minimal activity at time of inspeciton
Correction needed: - sweep Federal Way in front of entrance and in turn lane.
|
General Inspection | 10/13/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Andy J. Long
|
|
|
Permit sign and SWPPP info posted at construction entrance. Building frame has now been erected but no site improvements or landscaping. Perimeter silt fence is installed around site, no trackout or fugitive dust issues. Approved.
|
General Inspection | 10/10/2016 | 10/10/2016 | 10/13/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
Evan Jenkins
|
|
|
work occuring on footings. No ESC issues observed at this time
|
General Inspection | 8/4/2016 | 8/4/2016 | 8/5/2016 | P | PASS |
Andy J. Long
|
|
|
Permit and SWPPP sign posted. No trackout to Federal Way, no fugitve observed. Onsite inspecitons conducted by contractor and Micron - no issues reported.
|
Random Inspection | 7/6/2016 | 7/6/2016 | 7/6/2016 | A | PASS |
Andy J. Long
|
|
|
Site BMPs installed. Permit sign posted at entrance. No trackout, no fugitive dust observed. Water truck on site. Approved.
|
Tracking Control | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Andy J. Long
|
|
|
Track out that was reported has been cleaned up. Rock construction entrance installed. Will need to stay vigilant but clean up has taken place in a timely manner.
|
Site Preparation | 6/8/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Andy J. Long
|
|
|
meet with Zwick Construction @ 9:30 AM
SWPPP contacts: Derek and/or Arn
BMPs installed: - rock construction entrance to control trackout - perimeter silt fence to control runoff and wind erosion along ground surface - yellow permit sign to be posted with Zwick sing and CGP eNOI tracking #
- Water truck provided by Tuffy (excavation sub-contractor) Filling at company yard. Applying water to dump truck haul road route. No fugitve dust at time of inspection
RP & Tuffy will monitor trackout . Recommend using broom attachment on tractor rather than broom sweeping due to traffic.
WIP. Approved for construction.
|
Random Inspection | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PART |
Andy J. Long
|
|
|
Construction entrance & silt fence perimter BMP installed. Water truck on site to control fugitve dust.
Corrections requested to RP Dawn: - have contractor post SWPPP info and Boise ESC permit. (stated that job trailer to be brought on site today) - schedule site prepartaion inspection with on-site SWPPP inspector/RP Arn next week.
No trackout or discharges, no dust plumes crossing property lines.
Will check in later this week.
|
General Inspection | 5/4/2016 | 5/4/2016 | 5/4/2016 | | NR |
Andy J. Long
|
|
|
No activity or staging at site at this time
|