General Inspection | 7/29/2016 | 7/29/2016 | 7/29/2016 | | PASS |
Andy J. Long
|
|
|
Townhome complete. Subdivsion BMPs in good condition. Active projects ongoing. RP onsite. All permits finaled.
|
DOC - Permit Finaled | 7/29/2016 | 7/29/2016 | 7/29/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/13/2016 | 6/13/2016 | 6/13/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/26/2016 | 4/26/2016 | 4/26/2016 | | PASS |
Andy J. Long
|
|
|
WIP on clubhouse and pool area.. Subdivision BMPs installed and RP onsite daily for supervision and cleanup.
|
BMP Violation | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | FAIL |
Andy J. Long
|
|
|
Subcontractor crane leaked significant amount of fluid (hydraulic oil?) on Blue Ribbon.
Requested that soil spread around spill area be swept immediately and disposed of properly to not mix with the storm water from today's afternoon precipitaion.
Both Brighton Corp. & Brighton Homes are working on case. Kyle stated he will give crane operator a warning to bring spill prtection and cleanup materials. Company is AM Crane, which I was unable to contact.
Corrections in progress
|
General Inspection | 2/10/2016 | 2/10/2016 | 2/10/2016 | | PASS |
Andy J. Long
|
|
|
WIP at Park Place. DI bags were changed out last wek as requested. New lined washout in place and working well. Employee working at cleaning out sediment in gutters at time of inspection. No discharges or trackout off-site.
|