General Inspection | 9/5/2016 | 9/5/2016 | 9/6/2016 | | PASS |
Andy J. Long
|
|
|
Work complete and storage units are in use. DI bag on River & 13th to remain intalled of adjacent project ESC15-01552.
All permits finaled, no further ESC inspections.
|
DOC - Permit Finaled | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/19/2016 | 8/19/2016 | 8/19/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 8/4/2016 | 8/4/2016 | 8/4/2016 | | PEND |
Andy J. Long
|
|
|
to be finaled with adjacent project completion due to shared BMPs and access area
|
General Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PEND |
Evan Jenkins
|
|
|
some minor re-veg still needs to occur. all others permits are closed. ESC conditions almost satisfied
|
General Inspection | 7/5/2016 | 7/5/2016 | 7/5/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 6/20/2016 | 6/20/2016 | 6/20/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/3/2016 | 6/3/2016 | 6/3/2016 | | PEND |
Evan Jenkins
|
|
|
remove all TEMP BMP's. Next inspection with this issue not resolved will result in a reinspection fee
|
General Inspection | 5/19/2016 | 5/19/2016 | 5/19/2016 | | PEND |
Evan Jenkins
|
|
|
Remove Temp BMP's
|
General Inspection | 5/4/2016 | 5/4/2016 | 5/4/2016 | | PASS |
Andy J. Long
|
|
|
Work complete. Surrounding area still utilized as staging area for project on adjacent parcel. Temp BMPs still installed. Will monitor for final clean up and temp BMP removal
|
Random Inspection | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Andy J. Long
|
|
|
WIP at Idaho Self Storage on River Street. No loose sediment or discharges leaving site. Parking lot is paved, landscaping not yet installed. No violations observed, clean site.
|
Random Inspection | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PASS |
Andy J. Long
|
|
|
Clean site, no trackout. BMPs installed.
|
General Inspection | 2/3/2016 | 2/3/2016 | 2/3/2016 | A | PASS |
Andy J. Long
|
|
|
WIP. No trackout. Perimeter sidewalks and gutters are clean and free of sediment from site.
New project by same builder has started on adjacent lot, see ESC15-01529.
|
General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on vertical construction at River Street Storage. Site perimeter is surrounded by structural sediment barriers in the form of curbing and sidewalk(some new some existing). Disturbed area surrounded by security fence to control access. Staging area is being shared in parking lot of Pioneer where Payette Brewing project is underway.
No trackout. No muddy discharges. MS4 on River and 13th has sediment filter bag. Yellow permit sign posted. Site is well kept. No corrections at this time.
|
General Inspection | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation and platform for River Street Storage. Permit sign posted, access controlled via construction entrance. No trackout or discharges observed; DI bags installed. Approved.
|
Site Preparation | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PASS |
Andy J. Long
|
|
|
Note - ESC site walk through and conference initially conducted prior to permit issue...
WIP. Permit sign posted, water truck on site to control dust and for complaction. Very flat site - BMPs currently include stabilized entrance, DI bag on 13th & River St. and keeping exisiting sidewalks above grade of loose dirt with preservation of buffer as much as possible.
|