Information based on query as of Tuesday, June 18, 2024.
Permit Information
Permit NumberESC15-00955
StatusFinaled
Name JEFF KORSEN
Site Address 2815 S MAPLE GROVE RD
Project NameNew Molenaar City Park
Customer Number 
ePlanReviewNo
Description
Construction of New City Park: (Molenaar Green Up) - Grading permit to excavate, grade and compact site earth materials in preparation for the New City Park. Underground utilities only, no buildings or footings are allowed to be constructed under this permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection10/30/201710/30/201710/30/2017 CANC
DetailsMichael Zawacki
DOC - Permit Finaled10/30/201710/30/201710/30/2017PPASS
DetailsMichael Zawacki
General Inspection9/12/20179/12/20179/13/2017 CANC
DetailsAndy J. Long
General Inspection7/28/20177/28/20177/28/2017 PASS
DetailsAndy J. Long
Park grading, vegetatation, and bathroom installation complete. Not fully open till public. Some work occuring around ponds in southwest corner. Will check for site final next inspection.
General Inspection6/12/20176/12/20176/13/2017 CANC
DetailsAndy J. Long
General Inspection4/25/20174/25/20174/25/2017 CANC
DetailsMelissa Jannusch
General Inspection3/10/20173/10/20173/10/2017 CANC
DetailsAndy J. Long
General Inspection1/23/20171/23/20171/26/2017 CANC
DetailsAndy J. Long
General Inspection12/6/201612/6/201612/6/2016 CANC
DetailsAndy J. Long
No inspection. Park complete and is currently in the vegetation process. Will continue to monitor
General Inspection10/21/201610/21/201610/21/2016 PASS
DetailsAndy J. Long
Molenaar Park is near completion. Final landscaping and some site work remains. Parking lot is finished and permeable asphalt is installed. No mud or dirt stockpiles in drainage area.

Open space has been planted with grass and trees planted. Permit and SWPPP info posted at entrance. No violations observed.
General Inspection9/5/20169/5/20169/6/2016 PASS
DetailsEvan Jenkins
General Inspection7/21/20167/21/20167/21/2016PPASS
DetailsAndy J. Long
WIP on park lansdcaping and features. Parking lot is paved. No trackout or discharges offsite. No fugitive dust plumes observed. No corrections requested at this time.
General Inspection6/17/20166/17/20166/17/2016 PASS
DetailsAndy J. Long
Park grading is complete. Landscaping is in progress. Parking lot is now paved. No trackout, fugitive dust observed. Minimal site activity at time of inspection.
General Inspection4/28/20165/2/20165/4/2016APASS
DetailsAndy J. Long
No fugitive dust, no trackout. Earthen landscape features and paths being installed. Water feature will soon be landscaped. Permits posted, no corrections issued.
General Inspection4/27/20164/27/20164/28/2016 CANC
DetailsAndy J. Long
rescheduled for 5/2
General Inspection3/8/20163/8/20163/8/2016PPASS
DetailsAndy J. Long
Minor work in progress on landscaping park features. No trackout, permit sign ans SWPPP information is posted. No corrections issued, no violations observed.
General Inspection2/1/20162/1/20162/1/2016PPASS
DetailsAndy J. Long
Site currently inactive. Parking lot is complete, but still connected to roadway via rock entrance to prevent trackout. Any previous trackout that occured has been adequately cleaned. Site is now graded and will be ready for landscaping activities this Spring. No corrections. Yellow permit sign and SWPPP info posted.
Tracking Control10/19/201510/20/201510/20/2015PPART
DetailsAndy J. Long
Trackout complaint called in 10/19 for Molenaar Park project. Inspect for clean up and condition of construction entrance.

Some trackout has occured but appears that street has been swept since time of complaint as there was no significant accumulations. Parking lot will soon be paved, thus eliminating tracking problem. Will continue to monitor and will request maintainacne on the current rock stabilized entrance if parking lot is not to be completed within the next few weeks. No other issues observed.
Tracking Control10/19/201510/19/201510/19/2015PPART
DetailsJim Little
Talked to Jeff, they will clean up mud on maple grove and move entrance back to track out area once trench is backfilled at end of day.
General Inspection10/5/201510/5/201510/5/2015PPASS
DetailsAndy J. Long
Molenaar Park WIP. Permit posted at entrance, no significant trackout or fugitive dust observed. Water trucks are on site for dust control and construction entrance is installed. No issues observed and no complaints received recently. Approved
Complaint Inspection8/25/20158/25/20158/25/2015PPART
DetailsAndy J. Long
Trackout complaint received.

Trackout is occuring onto Maple Grove to the bike lane and slightly into the southbound traffic lane.
The trackout issue is due to fugitive dust control efforts by water truck, which is more of a priority at this time.

Correction issued to onsite supervisor Brent to turn over rocks in construction entrance and sweep up bike lane area (which is to be closed by ACHD).
Site Preparation8/21/20158/21/20158/21/2015PPASS
DetailsAndy J. Long
Molenaar Park grading and site development:

Construction entrance installed. SWPPP sign and City of Boise ESC permit posted. Water truck on site for dust control, though it is quite windy so some dust.

Approved.