Aging Inspection | 9/11/2017 | 9/11/2017 | 9/13/2017 | | PASS |
Andy J. Long
|
|
|
|
DOC - Permit Finaled | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 7/10/2017 | 7/10/2017 | 7/10/2017 | | PEND |
Andy J. Long
|
|
|
water line upgrade/utility trenching in progress in roadway, area not yet stabilized. No discharges
|
Aging Inspection | 5/8/2017 | 5/8/2017 | 5/9/2017 | | PASS |
Andy J. Long
|
|
|
Project complete with temp. occupancy - BLD open for new water line work to be completed. No ESC corrections requested. ESC ok for final with BLD
|
Aging Inspection | 3/6/2017 | 3/6/2017 | 3/6/2017 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 1/2/2017 | 1/2/2017 | 1/3/2017 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 10/31/2016 | 10/31/2016 | 10/31/2016 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 8/29/2016 | 8/29/2016 | 8/29/2016 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 6/28/2016 | 6/28/2016 | 6/28/2016 | | PASS |
Andy J. Long
|
|
|
WIP on in private community. No discharges, loose debris or sediment leaving site.
|
Aging Inspection | 4/27/2016 | 4/27/2016 | 4/27/2016 | | PASS |
Andy J. Long
|
|
|
|