Permit NumberESC15-01060
StatusFinaled
Name STEVEN HANSON
Site Address 5304 N HILL RD
Project NameMoore Residence Hill Road
Customer Number 
ePlanReviewNo
Description
Construction of new foothills SFH on Hill Road. Driveway and site grading for homesite has already been completed previously. Total parcel size is 5 acres, only 0.5 earth disturbance per SWPPP submittal. BMPs include perimeter sediment control wattles along at limits of disturbance, preservation of existing hillside vegetation that surrouds home and detached garage site. Site walk through and BMP preparation inspection is required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final12/2/201612/5/201612/5/2016PPASS
DetailsAndy J. Long
Erosion and sediment controls on hillside SFH drainage area arre retaining sediment on site with a series of rock check dams. Wattles also keep sediment runoff from going on to driveway and down to Hill Road.

Hillside bond with ESC conditions included has been issued and home is now occupied. Syringa Construction no longer on site. No further ESC inspections.
General Inspection12/2/201612/2/201612/2/2016 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection11/17/201611/17/201611/18/2016 CANC
DetailsAndy J. Long
General Inspection11/2/201611/2/201611/2/2016 CANC
DetailsAndy J. Long
General Inspection10/18/201610/18/201610/18/2016 CANC
DetailsAndy J. Long
General Inspection10/3/201610/3/201610/3/2016 PASS
DetailsAndy J. Long
No changes at site since prior inspection. Still in stabilization/revegetation process
General Inspection9/16/20169/16/20169/16/2016 PASS
DetailsAndy J. Long
Home is complete and occupied. Not all slopes have vegetated. Drainaige channel lined with check dams. Will continue to monitor for performance during upcoming rain events in the Fall.
Random Inspection9/1/20169/1/20169/1/2016PPEND
DetailsEvan Jenkins
check re-veg status and temp bmp removal

Remove Temp BMP's. Fully re-vegetated
Random Inspection8/25/20168/25/20168/25/2016PCANC
DetailsEvan Jenkins
Check for re-veg
General Inspection8/22/20168/22/20168/22/2016 PEND
DetailsEvan Jenkins
remove temp BMP's
General Inspection8/5/20168/5/20168/5/2016 PEND
DetailsEvan Jenkins
SFH complete and occupied.
pending for minor re-vegetation and removal of temp bmp's
General Inspection7/21/20167/21/20167/21/2016 PEND
DetailsEvan Jenkins
re-vegetation
General Inspection7/6/20167/6/20167/7/2016 PEND
DetailsAndy J. Long
Home is complete and hillside revegetation/stabilization bond has been received. Many temp and permanent BMPs still installed. Need to conduct site final to determine which should be removed and which shall remain. No violations. Home appears to be occupied. All other permits finaled.
General Inspection6/21/20166/21/20166/21/2016 PASS
DetailsEvan Jenkins
retaining walls complete and disturbed areas above have been hydroseeded. New road has been paved. Bottom road has been swept.
No ESC issues observed
Random Inspection6/6/20166/6/20166/6/2016PPASS
DetailsEvan Jenkins
Rock Retaining wall complete.
No ESC issues observed at this time
General Inspection6/3/20166/3/20166/3/2016 PASS
DetailsEvan Jenkins
corrections have been made as requested
Random Inspection5/19/20165/19/20165/19/2016AFAIL
DetailsEvan Jenkins
Trackout Control

Significant amount of trackout from top to bottom of N. Hill Rd. from SFD construction. Additional BMP's need to be installed. Contacted RP Steve Hanson and left VM disclosing issues and to get them corrected asap due to expected rains though the weekend
General Inspection5/12/20165/12/20165/13/2016 PASS
DetailsEvan Jenkins
BMP's still in place.
Work on new rock retaining wall in progress.
No Issues observed at this time.
All disturbed areas becoming re-vegetated
General Inspection4/27/20164/27/20164/27/2016 PASS
DetailsEvan Jenkins
WIP: no esc issues observed at this time
General Inspection3/31/20163/31/20163/31/2016PPASS
DetailsAndy J. Long
Silt fence around home is re-installed properly. Numerous wattle and rock check dam have been installed on the cut area where water is running down hill.

Need to install roof top gutters and drainage system to prevent future problems.

Deposited sediment and sand has been swept up. Some erosion on access road below driveway entrance has pre-existing erosion rills and lack of stormwater conveyance.
Conference3/24/20163/24/20163/24/2016PDONE
DetailsAndy J. Long
Phone call from Wood Bros. ESC crew regarding corrections at site.

Notified that WIP on cleaning up displaced sediment, maintaining check dams, and ordering more BMPs (silt fence, wattles) to install later today or tomorrow.

Will check in tomorrow
Complaint Inspection3/23/20163/23/20163/23/2016PFAIL
DetailsEvan Jenkins
complaint from neighbor being flooded out from discharges from construction site

Large rainstorm overwhelmed both silt fences and straw waddles, discharging turbid water/sediment offsite down the road into a neighbors property.
Corrections:
1.) Repair and re-install all silt fence.
2.) Perform maintenance on all straw waddles.
3.) Rake out all rills and gullys
4.) Sweep up road.
Called RP Steve but he is out of town. Contacted Lisa (assistant) disclosing violations and she stated she will call Wood Bro's asap and have them up here today to begin maintenance. Will re-inspect tomorrow
General Inspection2/23/20162/23/20162/23/2016PPASS
DetailsEric Story
site looked good all barriers in place
Site Preparation11/19/201511/19/201511/19/2015APART
DetailsEvan Jenkins
A series of straw waddles and gravel check dams installed throughout the project, along with Silt Fence at top of project where SFH will be constructed. SWO removed.

Correction

-Rake out Rills, reinstall straw waddles on lower section that have become full of sediment from previous rain event (maintenance)
BMP Violation10/23/201510/26/201510/26/2015AFAIL
DetailsEvan Jenkins
BMP Violation Followup

No Corrections have been made. Have not heard back from contractor
Complaint Inspection10/23/201510/23/201510/23/2015PFAIL
DetailsEvan Jenkins
Sewer work: hillside damage

--Significant hillside Erosion taking place: No Permit Posted, No BMP's Installed. Called Steven Hanson w/ Syringa Construction (850.8424) left VM to call me back. WIll reinspect Monday morning