Permit Information
Permit NumberESC15-01061
StatusFinaled
Name David Moorhouse
Site Address 474 N STRATA VIA PL
Project NameLaney Residence
Customer Number 
ePlanReviewNo
Description
New single family residence: WUI Zone A; Permit for the construction of a new 5,490 sq. ft., two story with a basement (first story 2,833 sq. ft., second story 595 sq. ft., basement level 2,062 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 944 sq. ft. of covered patio/porch and a 2,028 sq. ft. attached garage
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/8/20167/8/20167/8/2016 PASS
DetailsAndy J. Long
Home complete. DI bag removed from down stream storm drain. Yard is landscaped, home occupied. Homeowner responsible for rock pile on adjacent lot.
DOC - Permit Finaled7/8/20167/8/20167/8/2016PPASS
DetailsAndy J. Long
Site Final6/14/20166/23/20166/23/2016APEND
DetailsEvan Jenkins
Remove temp bmp's. continue re-veg process
General Inspection6/14/20166/14/20166/14/2016 PEND
DetailsAndy J. Long
Landscaping in progress and access road built to back of house on the adjacent lot. This will need stabilization. Need to remove DI bag that is closest to house to the East..

BLD already finaled.
Site Preparation5/27/20165/27/20165/27/2016PPASS
DetailsJames Ady
final ok
General Inspection5/26/20165/26/20165/27/2016 CANC
DetailsAndy J. Long
General Inspection5/11/20165/11/20165/11/2016 PASS
DetailsAndy J. Long
WIP. Silt fence perimeter and DI sediment filter bag are in good condition. No windblown trash leaving property, no trackout, permit sign posted. No corrections requested.
General Inspection4/22/20164/22/20164/22/2016PPASS
DetailsAndy J. Long
WIP. Silt fence perimeter installed and permit posted. No trackout. STreet, sidewalk and gutter are free of loose dirt and debris. No trackout or discharges. Approved.
General Inspection4/4/20164/4/20164/4/2016PPASS
DetailsAndy J. Long
WIP. Silt fence BMP is installed. Sidewalk and gutter have been regularly swept. No trackout or spills in front of site. Trash and materials are contained. No corrections needed at this time.
BMP Violation2/16/20162/16/20162/16/2016PPASS
DetailsAndy J. Long
Corrections completed as requested. Unfinished driveway blocked with silt fence. Silt fence re-installed in areas where it came untrenched. Sidewalk and gutter were swept.

Notice removed from site.
Tracking Control2/12/20162/12/20162/12/2016PPART
DetailsAndy J. Long
Trackout and loose sediment coming off site to sidewalk, gutter and road from the incompleted driveway without stabilization.

Correction request posted:
- sweep up loose dirt in gutter, sidewalk and street in front of project.

No discharges or other violations observed. Silt fence installed along sidewalk frontage.
General Inspection1/14/20161/14/20161/14/2016PPASS
DetailsAndy J. Long
WIP. No significant trackout, no discharges. Most of silt fence is still trenched in and keep sediment off sidewalk and onsite.
Tracking Control12/16/201512/18/201512/18/2015PPASS
DetailsAndy J. Long
Street and sidewalk were swept as requested. DI bag is installed and capturing sediment and filtering runoff.

No activity in mud. Silt fence installed is trenched properly and damaged sections removed. Approved.
Tracking Control12/14/201512/15/201512/16/2015ACANC
DetailsAndy J. Long
snow delay, will check conditions Friday
Tracking Control12/11/201512/14/201512/14/2015PCANC
DetailsAndy J. Long
rescheduled 12/15 AM
General Inspection12/10/201512/11/201512/11/2015AFAIL
DetailsAndy J. Long
Muddy trackout and runoff from disturbed unstabilzed entrance:

Corrections and maintenance needed:
- repair silt fence

- install construciton entrance or block driveway access with sediment control BMP
- Remove mud clods and sweep gutter and change out DI bag

Verbal CN issued to RP and GC. Will check Monday PM
Site Preparation10/14/201510/14/201510/14/2015PPASS
DetailsAndy J. Long
Silt fence installed, rock on site to be used for tracking pad. GC onsite, will install DI bag to the east down Strata Via.

Approved for construction. BMP install by Syman Co.