Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberESC15-01068
StatusFinaled
Name AARON MEGEE
Site Address 2008 S KERR ST
Project Name 
Customer Number 
ePlanReviewNo
Description
As per ESC Conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final6/20/20166/20/20166/20/2016PPASS
DetailsEric Story
site final ok
Complaint Inspection1/19/20161/19/20161/19/2016PPART
DetailsAndy J. Long
Trackout on sidewalk and roadway.

BMPs installed and no discharges, but mud on sidewalk and street in front of projects should be swept. Verbal CN issued to builder.
Site Preparation1/19/20161/19/20161/19/2016PCANC
DetailsAndy J. Long
data entry error
General Inspection12/22/201512/22/201512/22/2015PPASS
DetailsAndy J. Long
CN follow up inspection. Wattle now installed along Kerr Street as requested. Sidewalk was cleaned at end of day. Oil sheen has been absorbed to a certain extent by the floor dry put down and is no longer visible in runoff down the gutter.
BMP Violation12/21/201512/21/201512/21/2015PPART
DetailsAndy J. Long
Loose dirt and mud swept off sidewalk and street. Backfill stopile was pushed further away fro sidewalk.

New DI bag installed

- oil sheen is still quite visible. Need to put more floor dry down and sweep up old floor dry.
- need to install a wattle along the sidewalk until backfill stockpile can be removed.
Complaint Inspection12/18/201512/18/201512/18/2015AFAIL
DetailsAndy J. Long
Complaint of muddy site received by Code Enforcement hotline...


Inspection observations:
- Flat infill lot, 4 SFHs same builder
- Concrete just poured probably yesterday. Excavated dirt for backfill is next to sidewalk. Very wet mud, some runoff and clods on sidewalk going to gutter.
- Looks like concrete truck or pump crane leaked some fuel and there is a sheen on roadway and runoff..
- Receiving DI is 1 block to the west on Palouse and Hervey. No DI bag installed.
- Permit signs are posted.

Corrections:
- sweep sidewalk, provide stockpile buffer strip so no soil is on sidewalk. Install wattle as necessary
- put spill absorbant on spill in road in front of project

Verbal CN issued to RP-GC Aaron Mcgee

RP stated he will be onsite with spill absorbant and broom ASAP this afternoon and will check in