Site Final | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PASS |
Andy J. Long
|
|
|
Street and gutter has been swept. All landscaping complete. ESC permit conditions satisfied. All permits finaled.
|
General Inspection | 6/1/2016 | 6/1/2016 | 6/1/2016 | | PEND |
Andy J. Long
|
|
|
Home complete and BLD finaled, final landscaping in progress. No temp BMP removal needed but requested that street, sidewalk, and down stream sediment from site be removed from gutter in order to final ESC permit.
|
BMP Violation | 5/16/2016 | 5/16/2016 | 5/16/2016 | P | FAIL |
Andy J. Long
|
|
|
Crews washing equipment and mixing cement on sidewalk/roadway (Aggregate & Clements).
Requested to worker on site to move all equipement off sidewalk and contain any wash water. Once dry the area should be swept.
|
General Inspection | 5/12/2016 | 5/12/2016 | 5/13/2016 | | PASS |
Andy J. Long
|
|
|
Project is still active but near completion. No ESC corrections needed.
|
General Inspection | 4/27/2016 | 4/27/2016 | 4/27/2016 | | PASS |
Andy J. Long
|
|
|
WIP on landscaping and finishing touches on interior. Lots of activity, will need to sweep up at end of day. No significant trackout, no discharges.
|
General Inspection | 4/12/2016 | 4/12/2016 | 4/12/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 11/20/2015 | 11/20/2015 | 11/20/2015 | P | PASS |
Andy J. Long
|
|
|
ESC permit sign posted clearly. Wattles installed at toe of slope at bottom property line. No litter or debris around site. No activity at time of inspection.
No trackout, illicit discharges or othe violations occuring at site. In compliance.
|
Site Preparation | 10/20/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Andy J. Long
|
|
|
Erosion control pre-dig site meeting. Please call STeve with a time to meet. thanks, steve 850.8424 Phone #: ###-#### Inspection requested via web by steve hanson
Permit sign is posted with contact information. Sediment control perimeter wattles have been installed at toe of slope and existing woodplank fence as well along west property line.
Due to clay soils and issues it may cause with foundation (engineered slab), significant offhauling of dirt and subsequent infill will be first phase of project.
Once this is complete, lined washout pit will be installed as well as construction entrance. Approved for excavation.
|