Aging Inspection | 4/13/2016 | 4/13/2016 | 4/13/2016 | | PASS |
Andy J. Long
|
|
|
Work complete. Home in process of being landscaped by homeowner. Grading below sidewalk/pavement edges, no loose stockpiles or materials. No further ESC inspections on this permit. Temp BMPs in RH#6 to remain until all SFH work is complete.
Brighton HOmes RP onsite with many open ESC permits for any corrections needed in RH#6
|
DOC - Permit Finaled | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 | P | PASS |
Eric Strole
|
|
|
|
Site Preparation | 9/23/2015 | 9/24/2015 | 9/24/2015 | P | PASS |
Andy J. Long
|
|
|
Yellow card on site Inspection requested via web by Erby Gonzales
Many SFHs in new RH#6 phase are in progress. Subdivision BMPs installed. Will need street sweeping this weekend. Approved to start. No residents in subdivision, no trackout or offsite discharges observed.
|