Site Final | 5/19/2017 | 5/19/2017 | 5/19/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 5/19/2017 | 5/19/2017 | 5/19/2017 | | PASS |
Melissa Jannusch
|
|
|
Landscaping complete. All soil is stabilized. No temporary DI protection drainage into curb cuts and pavers. Pavement and sidewalks are swept and free of sediment. All temporary BMPS have been removed.
|
General Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/19/2017 | 4/19/2017 | 4/19/2017 | | PASS |
Melissa Jannusch
|
|
|
Landscaping occuring at time of inspection.
|
General Inspection | 4/4/2017 | 4/4/2017 | 4/4/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on interior and exterior. Before final ensure all temporary BMPs are removed.
|
General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 | | PASS |
Melissa Jannusch
|
|
|
Walk through with RP on site. Project nearing completion. Minimal earth disturbance. Perimeter of job site is clean. Concrete washout is full RP has maintenance scheduled. SWPPP inspections are up to date.
|
General Inspection | 3/3/2017 | 3/3/2017 | 3/3/2017 | | PASS |
Melissa Jannusch
|
|
|
Make sure residues from dirt pile are swept up next inspection. No corrections.
|
General Inspection | 2/16/2017 | 2/16/2017 | 2/16/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP. No corrections
|
General Inspection | 2/1/2017 | 2/1/2017 | 2/1/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on interior. No earthwork occurring. No corrections.
|
General Inspection | 1/17/2017 | 1/17/2017 | 1/23/2017 | | PASS |
Melissa Jannusch
|
|
|
Talked with Bruce RP. Site improvments and stormwater management already installed. Snow covered. WIP on the interior. No earthwork. staging area is clean. Reviewed SWPPP, site map, and inspections are avalible. PW also inspecting.
|
General Inspection | 1/2/2017 | 1/2/2017 | 1/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/15/2016 | 12/15/2016 | 12/16/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/30/2016 | 11/30/2016 | 11/30/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/15/2016 | 11/15/2016 | 11/15/2016 | | PASS |
Andy J. Long
|
|
|
WIP on Bown Library! branch. Site parking areas and pavers are installed. Impervious surfaces free of loose dirt/trackout. Liquid waste washout pans onsite. No ESC corrections neeeded
|
General Inspection | 10/31/2016 | 10/31/2016 | 11/1/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/14/2016 | 10/14/2016 | 10/14/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/29/2016 | 9/29/2016 | 9/29/2016 | | PASS |
Andy J. Long
|
|
|
WIP on Library structure. Curbing, paving and parking areas are complete. Some landscaping is also in progress. No dirt stockpiles or trackout on permeable paver drainage areas. Permit sign posted on trailer. Clean site.
|
General Inspection | 9/14/2016 | 9/14/2016 | 9/14/2016 | | PASS |
Andy J. Long
|
|
|
WIP on new Library! branch at Bown Crossing. Site parking lot, utilities and permanent storm water system is installed. No trackout, no discharges observed. Approved.
|
General Inspection | 8/30/2016 | 8/30/2016 | 8/30/2016 | | PASS |
Andy J. Long
|
|
|
New Library project has stabilized paving and stormwater infrastructure installed. WIP on structure. Trash and materials seperated and contained. No trackout,discharges, or fugitive dust observed. Approved.
|
General Inspection | 8/15/2016 | 8/15/2016 | 8/15/2016 | | PASS |
Andy J. Long
|
|
|
Materials onsite and concrete washout are contained. No trackout, fugitive dust, or discharges occring. Site is in compliance.
|
General Inspection | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | PASS |
Andy J. Long
|
|
|
Library foundation and footprint are complete. Walls and beams are erected. Site surrounded by construction fencing. Permanent stormwater retention system and parking lot paving is near complete, except for a few areas.
No fugitive dust, spills/discharges. Trash and materials contained. No corrections needed.
|
General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/11/2016 | 7/12/2016 | 7/12/2016 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/8/2016 | 7/8/2016 | 7/11/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 6/23/2016 | 6/23/2016 | 6/23/2016 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | PASS |
Andy J. Long
|
|
|
WIP at library. Site perimeter is in good condition and no sediment runoff or issues observed. Construction entrance with rumble bars is installed. No violations. Clean site.
|
General Inspection | 5/17/2016 | 5/17/2016 | 5/17/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: no issues observed at time of inspection on Library
|
General Inspection | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on Library! No trackout, no significant changes to SWPPP managemnt. Construction entrance and concrete washout area are installed. No corrections issued.
|
General Inspection | 2/24/2016 | 2/24/2016 | 2/24/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on new Library! at Bown Crossing. Trackout controls and waste management are well maintained and in good condition. Filtering wattles installed in perimeter runoff points within the security fence.
No violations observed. RP Bruce keeping good SWPPP records and performing inspections. Boise PW inspectors/managers monitoring SWPPP activity.
Approved.
|
General Inspection | 1/22/2016 | 1/22/2016 | 1/22/2016 | P | PASS |
Andy J. Long
|
|
|
No trackout from site. Construction entrance installed. Site perimeter is in good condition. No dewatering detected. No turbid discharges.
Approved.
|
Site Preparation | 12/22/2015 | 12/23/2015 | 12/23/2015 | A | PASS |
Andy J. Long
|
|
|
Bruce Phone #: ###-####
Site walk through and SWPPP review with RP Bruce and project manager Dennis with CM Company.
BMPs installed/implemented include perimter sediment control wattles, rock construction entrance with rumble bars to prevent tracking, a SWPPP binder on site with regular inspections. Ecopan concrete washout will be utilized for concrete work at site. Not yet on site.
Dewatering plan has been included in SWPPP with groundwater predicted to be at 5-9 feet at time of utility and foundation work. Current plan calls for pumping water into the irrigation canal that runs underground along the north side of site. Additional turbidity reduction measures are listed if needed as well as discharging into an onsite swale.
Construction to begin after beginning of the year.
Approved.
|