Site Final | 4/19/2016 | 4/19/2016 | 4/19/2016 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PASS |
Jim Sly
|
|
|
|
BMP Violation | 1/21/2016 | 1/21/2016 | 1/22/2016 | P | PASS |
Andy J. Long
|
|
|
Austin Phone #: ###-####
Corrections completed: - ESC permit sign posted in alley. - street sweeper went around block and looks much better. Manual sweeping should continue regularly as needed. - lined concrete washout provided - New DI bags installed in alley as requested - most of the windblown trash has been picked up - reinspection fee paid.
Approved. Site is back in compliance. RP will call in site preps for next 3 homes on Race in February.
|
BMP Violation | 1/19/2016 | 1/22/2016 | 1/21/2016 | P | CANC |
Andy J. Long
|
|
|
|
BMP Violation | 1/15/2016 | 1/19/2016 | 1/19/2016 | P | PEND |
Andy J. Long
|
|
|
Re-inspection fee paid. Will check back for site conditions and completion of corrections issued.
|
BMP Violation | 1/12/2016 | 1/15/2016 | 1/15/2016 | A | CANC |
Andy J. Long
|
|
|
Follow up on CN issued Tuesday 1/12
Compliance date extended due to recent snow/rainfall received
|
BMP Violation | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | FAIL |
Andy J. Long
|
|
|
Multiple BMP violations at site observed as well at ESC15-01349. Onsite inspection with RP Austin.
- no site prep inspection requested - no yellow permit sign posted at time of inspection - streets and sidewalk dirty with trackout without regular sweeping or housekeeping - trash and construction wrappings accumulated along Wildwood.
Corrections issued: - street, gutter, and sidewalk sweeping - change out inlet bag on alley - post yellow permit sign - provide designated concrete washout pit
Re- inspection and fee required. Written Correction Notice given to RP Austin. $55 re-inspection fee assessed to site. No parcel hold currently.
|