General Inspection | 10/7/2016 | 10/7/2016 | 10/7/2016 | | PASS |
Andy J. Long
|
|
|
Foundation work and landscaping work on retaining walls is complete. NO construction materials and activity on site. Permit for landscaping still open as front bank stabilizes. See ESC16-00269
|
DOC - Permit Finaled | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 9/8/2016 | 9/22/2016 | 9/26/2016 | P | CANC |
Andy J. Long
|
|
|
|
Site Final | 9/6/2016 | 9/8/2016 | 9/8/2016 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 9/6/2016 | 9/6/2016 | 9/6/2016 | | PEND |
Andy J. Long
|
|
|
No activity, construction appears to be complete. No dirt runoff or trackout. The yard needs to be vegetated or have perimeter sediment control before September is over and rain increases.
|
General Inspection | 8/19/2016 | 8/19/2016 | 8/19/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 8/4/2016 | 8/4/2016 | 8/5/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PASS |
Andy J. Long
|
|
|
New foundation is in, DI at Shenandoah was removed as requested (clogging up too much with leaf debris) and disturbed area is not yet stabilized but perimeter straw wattle is installed. No trackout or sediment runoff observed. Both BLD permits still open.
|
General Inspection | 7/1/2016 | 7/1/2016 | 7/1/2016 | | PEND |
Andy J. Long
|
|
|
|
General Inspection | 6/10/2016 | 6/15/2016 | 6/14/2016 | A | PART |
Andy J. Long
|
|
|
Need to change out DI bag. Request also issued to landscaping/retaining wall project under ESC16-00269
|
Aging Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|