Permit Information
Permit NumberESC16-00096
StatusFinaled
Name TRAVIS L PARKS
Site Address 1747 N FAIRMEADOW DR
Project NameVillage Charter School
Customer Number 
ePlanReviewNo
Description
(VILLAGE CHARTER SCHOOL)(BLDG 1) This project also being done in conjunction with BLD16-00161 on same set of plans. Remodel of an existing 24,500 sq. ft. office/retail building into new educational charter school with new classrooms and school administration offices per approved plans. New parking lot design and outdoor area for the kids.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final8/16/20178/16/20178/16/2017APASS
DetailsAndy J. Long
Parking lot, gutter, sidewalk, alley and intersection at Fairmeadow & Stonehaven has been swept. No temporary BMPs still installed. Site is landscaped/stabilized. ESC permit conditions satisfied.
General Inspection8/8/20178/9/20178/14/2017PPEND
DetailsAndy J. Long
BMP Violation8/7/20178/8/20178/8/2017APEND
DetailsAndy J. Long
Project manager Ron from Vertical called to state that intersection of Fairmeadow and Stonehaven have been swept as well as gutter. Street sweeping will also be performed when landscaping is complete.
BMP Violation8/7/20178/8/20178/7/2017APEND
DetailsAndy J. Long
Vertical 208 ###-####
Complaint Inspection8/7/20178/7/20178/7/2017PFAIL
DetailsAndy J. Long
Parking lot washed off with no sediment removal or sweeping.

Need to sweep gutter on Fairmeadow all the way to receiving storm drain.
General Inspection7/12/20177/12/20177/13/2017PCANC
DetailsMelissa Jannusch
General Inspection7/10/20177/10/20177/12/2017 CANC
DetailsAndy J. Long
General Inspection5/23/20175/23/20175/24/2017 PASS
DetailsMelissa Jannusch
Perimeter controls are installed. WIP on renovation of the parking lot. No trackout on Fairview or Fair Meadow.
General Inspection4/7/20174/7/20174/7/2017APASS
DetailsAndy J. Long
WIP on interior demolition & remodel. Selective demolition of curbing of previous use. Wattles installed around disturbed areas. No trackout or discharges. Dandy bag check dam placed in gutter since storm to capture sediment. Permit sign is posted.
General Inspection3/6/20173/6/20173/8/2017 CANC
DetailsAndy J. Long
General Inspection1/18/20171/18/20171/19/2017 CANC
DetailsAndy J. Long