DOC - Permit Finaled | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Andy J. Long
|
|
|
Home complete, landscaped, and ready to be occupied. Temp BMPs in East Valley to remain installed during active SFH construction on Ghost Bar.
|
Aging Inspection | 10/18/2016 | 10/18/2016 | 10/18/2016 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 8/17/2016 | 8/17/2016 | 8/17/2016 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PART |
Andy J. Long
|
|
|
Clint Phone #: ###-####
Permit sign posted. Exisiting projects are clean with streets having been swept. Approved for excavation.
Correction: - Tahoe to install new designated washout on Ghost Bar for the new phase with SFHs just starting on Ghost Bar and Boven.
Note: request to require Brundage Bone to provided a drip pan, tarp, or card board to contain oils from pump trucks.
|