Aging Inspection | 11/24/2016 | 11/24/2016 | 11/25/2016 | | PASS |
Andy J. Long
|
|
|
Work complete, all permits finaled. WIP in Park Place covered under ESC14-01083 . NO corrections needed.
|
DOC - Permit Finaled | 11/25/2016 | 11/25/2016 | 11/25/2016 | P | PASS |
Andy J. Long
|
|
|
|
BMP Violation | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Andy J. Long
|
|
|
Wallboard material that was washed out in gutter near inlet was cleaned and the DI bag with the collected material was replaced as requested. RP stated he will be installing a liquid washout station for painters, wallboardes and stucco workers.
|
BMP Violation | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | CANC |
Andy J. Long
|
|
|
compliance extended to tomorrow AM
|
Site Preparation | 8/31/2016 | 9/1/2016 | 8/31/2016 | A | CANC |
Andy J. Long
|
|
|
data entry error
|
BMP Violation | 8/31/2016 | 8/31/2016 | 8/31/2016 | A | FAIL |
Andy J. Long
|
|
|
Wallboard material and/or plaster material washout in gutter next storm drain within Park Place. DI filter bag full of solidfied material. Need to change out before end of the day. Will check back tomorrow AM.
Verbal CN issued to Erbie w/ Brighton
|
Site Preparation | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Andy J. Long
|
|
|
Inspection requested via web by Kyle Buzzell
Park Place townthome/condos are in progress. These 4 site preps are last 4 to start on the original phase of the project. Trash is contained, no windblown debris in park or Walling Creek area . Concrete washout pan is located on north side of Barber Station Dr. MS4 inlets have sediment filter bags installed and emptied every 2 weeks. RP Kyle onsite supervising.
|