Permit Information
Permit NumberESC16-00215
StatusFinaled
Name JEFF ARANT
Site Address 7136 N BOGART LN
Project NameMagnolia Park Upgrades
Customer Number 
ePlanReviewNo
Description
Note: SWPPP submitted meets City of Boise ESC plan requirements but not necessarily CGP SWPPP requirements. ESC plan calls for stabilized construction entrance and trackout controls, perimeter wattles and/or silt fence around perimeter discharge areas. Irrgation ditches and Boise City Canal open channels to be tuned into underground pipe. No dewatering plan is listed, groundwater at 6.5- 8 feet. Site preparation and installation of BMPs must be conducted and installerd prior to earthwork. Call 384-3802 or 794-8996
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final2/23/20172/23/20172/23/2017PPASS
DetailsMelissa Jannusch
General Inspection2/21/20172/21/20172/23/2017 PASS
DetailsMelissa Jannusch
Soil stable, vegetation mature, swale stable. Okay to final
General Inspection2/3/20172/3/20172/6/2017 CANC
DetailsAndy J. Long
General Inspection1/19/20171/19/20171/19/2017 CANC
DetailsAndy J. Long
General Inspection1/4/20171/4/20171/5/2017 CANC
DetailsAndy J. Long
General Inspection12/20/201612/20/201612/21/2016 CANC
DetailsAndy J. Long
General Inspection12/5/201612/5/201612/5/2016 PASS
DetailsAndy J. Long
WIP on park landscaping and re-vegetation. Parking lot is paved and frontage stormwater swales stabilized. No track out
General Inspection11/18/201611/18/201611/23/2016 CANC
DetailsAndy J. Long
General Inspection11/3/201611/3/201611/3/2016 CANC
DetailsAndy J. Long
General Inspection10/19/201610/19/201610/19/2016 PASS
DetailsAndy J. Long
Rough grading complete. WIP on parking lot , park features, and landscaping. No trackout to Bogart or Sloan. No discharges or fugitive dust occuring. Approved.
General Inspection10/4/201610/4/201610/4/2016 CANC
DetailsAndy J. Long
General Inspection9/16/20169/16/20169/16/2016 PASS
DetailsAndy J. Long
Park landscaping and irrigation line work in progress. Some localized dust, but no continuous plumes. No trackout or discharges occuring.
General Inspection9/1/20169/1/20169/1/2016 PASS
DetailsEvan Jenkins
no issues observed at time of inspection
General Inspection8/15/20168/15/20168/15/2016PPASS
DetailsEvan Jenkins
Random Inspection6/24/20166/24/20166/24/2016PPASS
DetailsEvan Jenkins
WIP: no discharges leaving site nor dust issues observed at this time
General Inspection5/9/20165/11/20165/11/2016PPASS
DetailsAndy J. Long
follow up inspection

Sediment and mud that was transported off north end of site has been cleaned up as requested. No new violations. Site back in compliance currently.
General Inspection5/9/20165/9/20165/9/2016AFAIL
DetailsAndy J. Long
Sediment runoff and mud from site has accumulated in the gutter on the south side of Sloan Street bordering the project.

No ESC inspections logged in the inspection on site, no construction entrance installed as listed in ESC plan.

Issued corrections to sweep and change DI bags to onsite supervisor for Diamond, Sam.